Interactive webcast player
Genesis Cinema Public Inquiry - Day Three
Thursday, 5th November 2026 at 9:30am
Speaking:
Welcome to our Webcast Player.
The webcast should start automatically for you.
Webcast cameras are not operated by camerapersons; they are automated and linked to speaker microphone units. The aim is to provide viewers with a reasonable visual and audio record of proceedings of meetings held in public.
Note: If your webcast link appears not to be working, please return to the Webcast Home Page and try again, or use the help email address to contact us.
Start of webcast
Share this agenda point
-
Webcast Finished
Disclaimer: This transcript was automatically generated, so it may contain errors. Please view the webcast to confirm whether the content is accurate.
Resumed. Just a couple of matters from my side. Firstly the site visit, so we're nearly through the
character and appearance evidence now, so I think we're at a stage where we can probably agree where I need to go.
So I was going to ask, could all three parties please liaise and agree a walking route, please.
And also, is it going to be possible to see inside the cinema, including inside the main auditorium?
So if that can be agreed please, both inside and around the site.
So that is scheduled for next week on Thursday, so perhaps that can be agreed before we open again on Tuesday.
I was going to say close of play Monday.
And if we could just confirm, I'm looking at Rule 6 here as much as anyone, just confirm
exactly who I need to visit.
I'll double cheque my own emails and evidence as well.
But just to cross reference, I'm not missing anybody out.
Thank you.
So we agreed yesterday that various topics would be added to the IDs.
They're not online yet. I don't know if that's the same issue as yesterday.
Just your colleague comes in about now then starts adding them.
Sorry, that would be the same issue. Yeah, there's more being sent.
So hopefully he wants, I think he's online now.
We should be able to add those.
Okay, so I'll just monitor that and then at lunch time we can discuss.
Although obviously we're finishing at one o 'clock today.
I've just seen an email as I sat down here with the SEL compliance statement.
So thank you for that.
Obviously I haven't read it yet.
Have you seen that?
I haven't personally.
I don't know if I'm just going to read it.
Okay thank you.
So I would accept that.
So that would be another ID document.
So that would be the next one.
And obviously I'll read that probably this afternoon once we adjourn.
Thank you.
Is there anything else that anybody else needs to raise before we turn to Dr Mealy?
Yes, so there's just a few points from my side.
Mr Warren and I had a brief conversation this morning in relation to your question on how
to manage the viability review mechanism issue and we've agreed that it makes more sense
to address you on this as part of the section 106 discussions, the mechanism on that, and
where parties will work together to see if we can come closer on anything in advance of that.
There's two other housekeeping points I wish to raise.
The first is a cabinet report has been brought to the Council's attention from a member of the development management team
who was watching the proceedings yesterday.
It's a cabinet report from July 2019 and one of the paragraphs and it's just paragraph 3 .6
Sets out the approach at least that was taken in
I'm sorry just to confirm this cabinet meeting concerned the local
listing local local listing and whether to approve a
number of buildings for local listing and paragraph 3 .6
explains the approach that was taken to that, specifically in respect of locally listing
in conservation areas and we thought that just given the discussion yesterday it would
be helpful for you to have it and I understand Mr Warren does not object to you seeing that.
So I would like to add that to the inquiry documents and I have copies for everyone,
I also have a copy for Dr Mille in case Mr Warren has any questions to direct to him
on that while he's giving evidence.
So that's the first issue.
So with your leave, sir, we'd like to introduce that.
If Mr. Baughan's happy, then I'm happy.
And the second document is an email
that yesterday afternoon our West Area manager
emailed Mr. Alastair Young from Historic England
to clarify whether he saw Bellevue Place
as part of the visit he took to the area.
And we have his response to that,
which he sent yesterday evening.
And so I have a copy of that email chain as well,
which we'd like to, again with your permission,
to add to the core documents and to provide to you.
And again, I have a copy for Dr. Mila if need be.
I'm happy to explain what it says, but it's very short.
Okay, yes, please add some geophysical copies.
Physical copies as well, yes.
Does he say that he did?
He says that he did not.
I did not, okay.
As it's so short, do you mind if I just take a moment just to read just now?
Yes.
OK, thank you.
Okay, thank you.
Thank you.
Anything from yourself, Mr. Oren?
No, thank you.
Ms. Taylor?
My understanding from yesterday and catching up on yesterday that there is still dispute
between the appellant and the Rule 6 party about the nature of the wall and its listing
status.
And our position is that it's listed sort of up to higher up on the wall than the appellant's
position is.
And there is some historic England guidance on listed buildings and curtilage from June
I haven't had the opportunity to speak to the other parties about this yet so I do apologise
for that but it essentially just provides some guidance on the case law that Dr Mille
mentioned in his evidence yesterday about how to take into account neighbouring buildings
when there's a listing and what amounts to curtilage.
Okay, thank you. Yes, then I accept that. Do you have a hard copy?
I unfortunately don't have a hard copy, but perhaps if I could email it, we could print
a hard copy, would that be possible?
As long as it eventually comes on the ID documents list, as long as Dr Meili and Mr Warren can
just access it online in the interim, that's fine by me.
Dr Meili's nodding like he knows what this is.
I've seen it before and I'm just getting it up to remind myself of it.
If I'm going to be asked questions, I'll just take a moment.
Absolutely, I'm happy for everyone to have an opportunity to look at it.
It was just an answer to the raising of the case law yesterday.
So if you are going to ask questions, perhaps a five minute adjournment to allow.
Thank you.
Okay.
Just to confirm, do we need to try and organise a printed copy during this adjournment for
everyone?
Perhaps, I also don't mind just going in the interim online.
Can you just confirm the exact name, please?
It's the Listed Buildings and Cartilage Historic England Advice Note 10 from the 17th of June
2025.
Okay with a picture of a thatched house and then a...
That's correct yes.
Okay, yes, I do have that, but obviously it will need to be added formally in due course.
Okay, thank you.
If that is everything, shall we then have a five -minute adjournment to say that Dr.
Moo can read this?
Okay, is five minutes enough, or would you like normal?
No, that's fine, I'm familiar with it already, so a quick reminder would be helpful, thank
you.
Right, 9 .39, so should we adjourn and come back at 9 .45?
Okay, thank you, the inquiry is adjourned.
It's quite awkward to walk down, aren't they? They're not quite described.
I haven't worked out the best way, still.
Okay, the inquiry is resumed.
Are we all ready to turn over to the Rule 6 and Dr Mealy?
Okay.
Ms Taylor.
Good morning, Dr Mealy.
Good morning.
I think Annie asked a couple of questions towards the end yesterday but forgive me I
might go over a couple of the same topics.
I'd first just like to ask you some questions in relation to the back garden.
Now I don't believe you've given any evidence that pertains to the back garden yet have
you?
The back garden of number 11.
The back garden is plural of the terraces at Bellevue Place.
I discussed it briefly yesterday but not in any detail.
Have you taken the back gardens into account when you're considering heritage points?
I'm not sure that I have in my written evidence, no.
And I explained yesterday, sir, that I thought that the rear of those terraces were relatively less sensitive from a heritage perspective
because of the way they've been extended and the secondary nature of those elevations.
Now do you accept that the back gardens form part of the listed status of the building?
They're part of the curtilage of the listed building obviously.
But the gardens themselves aren't listed.
Apologies, so you accept of course that the gardens both front and back form part of the listed status of the terraces?
Yes, as part of the curtilage of the listed building, absolutely.
And the curtilage is listed, of course, with those buildings?
No, I don't believe curtilage is listed, it's structures within curtilage.
I don't believe the land can be listed, but it's a legal point, so I wouldn't claim to be definitive on it.
The point of the curtilage provision of service is obviously to limit permitted development rights in certain circumstances in the immediate curtilage of the listed building.
So if we could turn to the Historic England guidance on listed buildings and curtilage
please.
It sets out some examples of adjacent properties and whether what conclusion Historic England
And if I could ask you to please turn to Figure 2 .3 on page 8.
Sorry, is that internal page or digital page?
My apologies.
It's digital page 8.
Thank you.
Figure 2 .3.
Yes.
Oh, apologies.
My PDF seems to have adopted the internal pagination.
Yeah, right.
But yeah, 11 of 25 it says at the bottom, apologies.
My reader has...
That's the example of a terraced house with mused buildings.
That's correct. So the terraced house in this example is listed as Grade 2.
And they consider whether...
They consider the purpose, which is in line with the case law.
Mm -mmm.
And do you accept that the Historic England Guidance has said that it changes its relationship with the listed house
But it would not be treated as part of the listed building
What is it? Sorry? I don't apologies in the answer box at the bottom of page 8
It considers yes, that's cool. Have the muse cottage been sold off prior to listing this would have changed its
Sorry, I haven't read it in that level of detail. Can I just take a moment to read the paragraph actually?
So this is the answer at the bottom of the page. We were looking at on terraces. Is that right?
Thank you very much. Just because it's a long quotation. I want to read it
Yes, I mean that's the practical application of the three.
I think there are four tests, sir, which is date of construction, ownership past and present,
ownership at the time of listing, and layout as well as function.
That's a fairly straightforward example of kurtil's listing, frankly.
And the wall in this case was there before 1948, do you accept that?
The whole of the wall that's there at the moment including, can I just ask for clarification,
can I just ask for clarification about which wall, the party wall with the cinema or the
low brick wall which was the former garden wall or a garden wall?
It's the submission of the Rule 6 party that the whole was there, but perhaps it would help to turn to your evidence and that diagram with the figures which can be found at page 15, electronic page 17 in your proof of evidence.
That's a fairly large photograph, isn't it?
Can you remind me, that's page 15 of my evidence, I believe.
Yes, physical page.
Oh yes, that's right, that's a nearly full page.
Yes, so if I can be asked the question with reference to this photograph, it would be helpful.
Do you accept that sections 1, 2 and 3 predate 1948?
Correct.
So you accept that that forms part of the consideration as to whether it's listed?
It does, but it's not the whole consideration.
because date of construction is also one
of the relevant legal tests and purpose.
And the other, one of the legal considerations, I mean legal,
from a practitioner's point of view, sorry, is what was there
at the time of listing.
So in this case, it's both pre -1948.
And critically, I think the listing here, post -dates 1969, it gets really complicated,
this post -dates 1969, there's no curtilage provision at, I think that's right, I can't
remember the date of listing of these properties, but if they were listed as I think is the
case after 1969, then yes, A, the curtilage provision provides.
The wall is pre -1948, therefore it's potentially curtilage as the whole thing.
Absolutely.
and it was there at the time of the listing, but the date of construction is not original
to the terrace, which is one of the considerations that the courts have taken into account in
these cases, and neither does the wall. The wall has a different purpose to the wall that
was constructed at the time of the terraces being built.
I'll come back to the purpose, but perhaps it would be useful to look at the listing.
So that's CD 4 .1 in Annie John's evidence.
Oh, thank you.
I have that printed.
Yeah, I have the CD.
Can I be given the reference again, please?
Page 23, please.
Are these the, can I ask if these are the photographs?
because unfortunately in the printing my page numbers were taken off.
Can I be shown the photograph?
Of course, it's this screenshot of the listing.
Oh, thank you, at the very back.
Okay, yeah.
The list in particular is the map.
That's correct.
Thank you very much.
Now, can you see at the bottom of the page it says 2 to 11 Bellevue Place.
Yes.
And on that, on the map itself right in the middle you can see Bellevue Place there, yes?
Yes.
Now
In our submission the Bellevue place is inclusive of the gardens and they're listed
With two to eleven Bellevue place and those gardens are part of the cartilage. Yes of those properties. I
Understand that
Due to the status and the of the wall and the length of time that it's been there
It's the position of the Rule 6 party that in your evidence at that diagram 1, 2 and
3, the listed element of the wall goes at least up to figure number 2 and that was at
page 15 of your proof of evidence.
Do you accept that?
I think I understand that's the Rule 6 party's position.
I don't agree with it myself as a practitioner.
because the three clearly was constructed more than 100 years
after the listed terrace and won,
and for an entirely different purpose.
And I don't know of you that the judge would take of it.
I can't ascertain that obviously,
and I'm just giving a practitioner's point of view.
But I would advise that three isn't listed.
And it seems to me, sir, the debate is really about two, really.
And just on the map and the current list entry, sir, the provisions introduced in 2015 around
listing do enable parts of structures to be excluded, as you may know, from the statutory
provision.
That process hasn't taken place here.
It takes some time, unfortunately, that process.
So I am of the view as a practitioner that tree is definitely not part of the listed
building, either by reason of curtilage or attachment, because it seems to me it would
be perverse for a listing of a structure of the nature we're talking about to give rise
to that level of designation to a larger adjoining structure.
But again, I can only give you my view as a practitioner and a chartered planner. Again,
restating the point one is undoubtedly both by reason of curtilage and more significantly
attachment because there are two provisions that we have to deal with under section 15
over the act, attachment and curdleage.
So, and I'm just going on like this, I'm sorry,
just to kind of focus the debate,
which I think is around two, and we heard yesterday,
you heard evidence from me yesterday, sir,
to the effect that I'd concluded two
was actually from the 1870s.
It was an altered wall, effectively the extension
of the northern wall of the passage,
and that was on the basis of images
that I interpreted in Miss John's evidence.
So, and I don't really know where that leaves things because if that's right, and I think
it's right, then 2 clearly post -states the construction of the terrace. And its purpose
would have been to create some kind of, well I can only guess at it really, I don't know
what its purpose was. It could have been part of the theatre to the east, or it could have
and part of the works that the brewery undertook, it's really completely uncertain.
And I think the point is moot in any case, sir, because under the terms of section 66
you have to consider the impact through the grant of planning permission on the special
interest of a listed building, and that is word for word the same test as you have to
So if you resolve to allow this appeal, then you would have taken the special interest
of that into account on the same statutory basis as section 16.
If I could ask you to turn to page 15 of Ms John's exhibit. I appreciate you've lost the numbers.
So if I just hold it up, it's this photograph.
Yeah, just give me a moment.
And that's electronic 23 for people working electronically.
Was it that one again?
Sorry.
No, okay.
It's got a little round thing on it.
Oh, this one.
Yes.
Yeah, thank you very much.
So that shows the view from the front and the wall going along on number 11, which is
Mrs. John's house at the end, yes?
Yes.
And if you turn back to page 12, so three pages before, to this photograph.
Yes.
Do you accept that there's a continuity of the brick that then goes along behind the
house?
In the middle section of the wall?
Yes.
I don't know what is behind the gable end of the terrace.
I can't say.
I'll take you to a photograph of the back garden in a moment, but for these purposes,
from the front of number 11 on the far left of the photograph, and then along the top
of the houses, do you accept that there's continuity of brick?
There's continuity of brick of the upper part, but I don't know if the wall is continuous
on the gable end of the house because it's a party wall, so how they treated that I honestly
can't say.
You wouldn't, if you're building adjacent to gable end of a party wall, necessarily
just use the same brick.
I have simply no idea.
Just to ask for clarity, is the question that section two of the wall, as helpfully we're
now calling it, is that present in the garden side too?
Was that the question?
I will get to section 2 in the back garden, I'm currently thinking of section 3 and that continuity above the houses in that photograph.
Yes, so to help with the point, I think excluding the gable end of the terrace about which I know nothing and I don't think we can ascertain,
the 1939 brickwork at the front of the terrace is the same as at the back, as far as I can judge from photographs of the back gardens.
So if we go to a photograph of the back garden which is the first photograph in the exhibit
bundle to Annie John's statement and that's electronic page nine.
Yes I've seen that photograph.
And again right at the top above number eleven and that's the same brick pattern as we saw
in the previous photograph.
Correct.
Do you accept that?
Yes.
And it continues on into her back garden.
The 1930s wall does. This photograph actually adds another layer of complexity, because in this photograph the lower part of the brick wall and you see a coping.
That, in my judgement, is part of the original construction of the terrace. You then get four courses of brickwork with a coping made from tile, which is mid -Victorian, so that's later.
And then you get this flush area of brickwork, which clearly is engineering brickwork but
doesn't have the same detailing that the brickwork above has.
So this part of the party wall and garden wall is even more complex than the other one.
And then there's actually a fourth area of dark red brick, the date of which I've
It's actually in Flemish Bond which is rather unusual.
I have no idea about that.
It's a complete puzzle.
But what is clear to me is that the 1930s brick that you see in this photograph which
is the pinky stuff is clearly not part of the original construction of the building
and the original garden wall goes up to that first coping and it has been pointed, you'll
see recently, or in this photograph anyway.
So in your section 2, it's the position of the Royal Sixth Party that that darker brick
at the same height as your section 2, would you accept that?
I can't make that judgement, no.
Because I don't have an elevation that details the coursing of that material across the gable
end of the terrace.
Turning to the next photograph, and this is facing away from number 11, looking at the
back garden.
So the…
Yes, so this is looking, sorry, don't cheque, this is looking south towards the former Wickham's
store.
That's correct.
Thank you.
And that's the mosque, I think.
The rear wall of the mosque?
I think it's looking towards the Wickham site.
This is page 2.
Apologies.
The exhibit is page 10 of the electronic.
I was just getting Google as well.
So I have that photograph.
Thank you.
And it's hard to see under the ivy, but can you make out that there's a chimney at the
cross section between the back wall and the party wall under the ivy?
The back wall being the sloping coping.
That's correct.
Sorry for that.
I see some projecting brickwork.
I don't know the evidence.
I can't see why that's a chimney as opposed to just a buttress or a pillar that you might
build at the junction of two garden walls, but I have no idea.
We'll have the opportunity at the site visit next week to look at this more closely as
number 11 is one of the properties we're viewing.
What I would say, again, to assist, because I'm not attending this inspection, but I would
say on this point, just to give you the benefit of my ability to understand historic fabric,
if you look at the right hand photograph, which is the detail, do you see there's been
lost, the fire face of the brick has been lost through cementitious pointing, so it's
flaking away?
And you see that bright yellow underneath the brownish top, that actually indicates
to me that stock brick from the late Georgian period, so that's probably from the 1820s
that brick.
So I would assume on the basis of this discussion that that stretch of brick wall, at least in part because we don't know, is probably part of the original terrace construction.
I say probably because it's in Flemish Bond which you don't expect for a garden wall but you know, it's more likely than that I think.
The position of the Rule 6 party, my understanding from my instructions is that there was a copper
fire here essentially and that was what the chimney was for in that area.
I have no reason to doubt that. I don't understand that that would be demolished as part of the
The development because it's a party structure which would need to be maintained
Under the terms of the act and through I'm sure a construction management plan
the proposal has a
Outside garden space for the students right above this garden, doesn't it?
Above to the east I think yes, there is can I just go to a plan to confirm what?
Yeah
Correct
Yeah, so yeah notes at the the reference sir, I mean there's in many places but the ground floor plan and just for your note
For example, it's at 7 .06 of the DAS, which is what I have, I don't have the drawing reference,
but I'm looking at it and it says, ground floor plan PBSA external amenity and there
are doors from the adjoining building so it must be at ground floor.
And the wall at that point is 4 plus metres retained is shown.
But I mean that has to be worked out during, you know, that's the intention of the way.
So if we were to go to electronic page 112 of Mr. Millet's proof of evidence, appendices.
Sorry mine.
Yes.
If that were your name.
Apologies.
CD 3 .2A.
Just one moment.
Sorry, one minute.
electronic page 112, which should match with the...
I think it does match, yeah.
Oh yes, this is the actual drawing, thank you.
I think, I believe this is the drawing submitted for approval.
That's my selection.
Okay.
I think we'll need to cheque this is against the drawing set,
and for some reason I'm not able to draw the Council's website at the moment.
Which is really irritating.
There we go.
Certainly it's 112 of the appendices.
So there's a drawing we looked at during my in chief.
Yes.
Now, Dr. Millet, that sort of white square next to the back garden of Bellevue Place,
that would be the garden of the proposed development, correct?
That's correct, at ground floor level, which is where the access is.
And then the wall that is proposed to retain a wall of up to 4 .4 metres plus at that point.
And you've accepted that you didn't consider the heritage impact to the back gardens,
but keeping in mind those photographs from Annie John's witness statement and the impact of the continuous brick wall,
Do you accept that there would be a negative heritage impact by that proposed development
to her back garden and the other back gardens at Bellevue Place?
Because the wall is retained.
In some form, the lower historic parts of the wall would be maintained as a party structure.
Well, the form is what's crucial, isn't it?
because the level that the wall is retained is just
over four metres, which doesn't capture the listed heritage
of the cartilage, which we say goes much higher
than four metres up the wall.
Do you agree with that?
No. I mean, the garden wall at that point, sir,
is under four metres.
That's clear from looking at the photograph.
So the entirety of what I judged
to be the original garden wall would be retained.
as a consequence, to achieve the 4m you would have to retain or indeed possibly rebuild
those other brick areas that we looked at which have at least two or three kinds of
brick in them. So I think it's more likely probably you'd have to rebuild those upper
parts to be perfectly honest, but I mean who knows, that just is something that has to
be worked out during construction, and if any special consents are needed they would
be applied for and obtained in the usual way.
You've said in your evidence that this is at 8 .74 on page 50 that proposals maintain
the strong sense of enclosure and in your evidence yesterday in relation to the front
of the property you discussed that you consider that there's no real difference essentially
between the neutrality of the continuous brick and the proposed development on that sense
of enclosure.
But do you accept that the wall is much lower in the back gardens?
Yes, I accept the wall is much lower but it would be maintained, it's proposed to be maintained
to four metres, four metres plus.
And so that would provide a strong definition to the extent of the rear garden.
And then a further building beyond that provides the same sense of, you know, being, as we
discussed yesterday being set away from the Myland Road next to a bigger building, which
is the experience now.
And just finally, I won't go over the evidence again which you gave yesterday in relation
to your view that the current brick wall is harmful, but do you accept that the people
who live there and their opinion of the war ought to be afforded more weight than yours?
No I don't accept that. What I accept is that as people living next to a development it's
right that the inquiry hears their views about how they perceive the impacts. With respect,
I don't think Ms Johns has my qualification in historic buildings or experience and neither
in Mr Parker, so I don't believe they presented any evidence, and again with the greatest
respect but of an expert professional nature. Obviously it's right sir that you hear what
they have to say, and I respect those feelings, I say this to Ms John, approaching it as a
professional which is a different frame of reference.
Any re -examination, Mr Warren?
Thank you very much.
You're welcome.
Thank you.
Yeah, just to mark on a...
I think so, sir.
Okay, welcome back everybody.
The inquiry is resumed.
First, did you manage to have discussions you needed on site visit?
That's the table four that has been produced in a hard copy from the review.
Okay, thank you. So I think next is cross -examination.
Mr Warren, just so you know, I'd probably like to take a break in about an hour, roughly.
But obviously, where there's a natural gap in your flow of questions, within reason, either side of that, if that's okay.
Thank you.
Good morning.
Good morning.
Mr Mello Browning.
May I just ask how you're set up in terms of the documents you've got open?
Have you downloaded any of them, the proofs or the other viability related documents that are on the core documents?
Or are you going to be going to them as we reach them one after the other?
So I have my proof of evidence, my rebuttal, appendix 3 and 4 Cushman and Wakefield documents and a few of the other core documents open.
But I don't have...
Okay, do you have Mr Brown's evidence open?
Mr Brown's evidence, yes.
Great great. I think that's fine
I mean we probably we might we will almost certainly go to a couple of those, you know call document nine point
You know the viability sub 19 or whatever in due course, but the main ones are the proofs and the appendices great. That's very helpful
Thank you
Could I ask you then to start I've got some quest to the structure of this is I've got some questions for you
by way of kind of overview and the approach and
And then I'm going to do, I hope, in a sensible order, a GDV, in the order that the items
and inputs appear in the FEAs.
I'm not going to be asking you, thankfully, every single point that you and Mr Brown raise
in your evidence.
I'm just trying to help the Inspector by focusing on what makes, we think, together the most
difference.
Okay, so could you start please by just going to your rebuttal proof of evidence?
And I don't know how it is in your electronic copy if you're looking on the screen, but
there is an appendix with an ARGUS FEA run.
Yes, appendix one, by the way.
It's page 15, I think it starts on, I've got at the bottom of the page helpfully.
This is an FEA exercise that you have carried out, I think, isn't it, on the 6th of October,
is that right?
So the date of this report is the 20th.
It says the 6th of October but I believe the rebuttal was submitted on the 20th.
Okay, it's just I thought that might, okay fine.
So it was done for the rebuttal, yeah?
Okay, thank you.
And it's called Stabilised Scheme Viability Appraisal.
Is that just a carry forward from the label if you like, the title of the previous versions of the FEA?
I'm not sure if it's being carried over.
I'd probably want to alter that title to part stabilised rather than stabilised, just for
reference.
Part stabilised, so we should rename it then part stabilised scheme viability appraisal.
Yes.
I see.
Okay, we'll come to the point about stabilisation obviously in due course.
Thank you.
But this FEA and all of its various inputs represents the latest state of play, doesn't
it?
This is your current evidence.
Yes, it does.
It does replace the former appraisal in my main proof of evidence.
And if we could, I don't know how easy this is for you on the screen, but if you could
So we have that still open and open Mr Brown's main proof of evidence, please, at page 22.
That's where he's got his table 2, which has his position, your position, and the difference
that it makes or made at the time.
Yes, okay.
So table 1.
A couple of pages further on or further down.
Age 20?
Yeah, page 22, it's just after 5 .3 .7.
5 .3 .7, right. Okay, so table 2.
You got that one. Table 2.
I do.
And obviously some of these figures, especially the consequential ones which are affected
by earlier inputs, have changed in relation to both the column which is THV position and
obviously then the financial difference column.
And I just wanted to just cheque on a couple of them if we can, just to try and help the
inspector update this table.
The PBSA valuation, which is the main box at the top, are you with me?
In terms of your net valuation figure, as at the date of this proof, it was 92 .84 million.
And I think it is now, isn't it, looking at your appendix 1, 96 .9?
So that is a valuation which includes the cinema valuation.
So the actual PBSA net valuation remains the same.
If you add the cinema to the 92 .8 million that will give you 96 .9 million.
So the net valuation of the student PBSA which is what that box is?
Remains the same.
Remains the same.
And so the financial difference of 11 .02 remains the same as well?
Yes.
Okay.
Thank you.
The overall differences between you in that case, I think is it right that if you look
right down at the bottom, obviously Mr. Brown's minus 9 .3 million, you're plus 8 .64.
Has that changed at all?
So yes I believe this is covered in the rebuttal so I can take you to the paragraph reference for ease so we can see that.
So if you go to paragraph 18 .1 of my rebuttal which is page 13.
So I display both James R. Brown's profit metric and my own.
call him Mr. Brown or James Brown I don't think he lives or dies by the R
I think that's the company name but we tend to call him James or Mr. Brown
yeah distinguished from the musician yeah featuring James R Brown I mean is it
sorry go on yeah so it reports both of our respective profit positions so
actually if we look if we were to if the inspector were to find James Brown's
profit on cost, my surplus would be 7 .9 million but based on my understanding of
profit on GDV, it would be 7 .2 million. So from 8 .6 to 7 .2 million would
be my analysis, it is higher if you were to take James Brown's profit on cost and
And that's due to the cost being slightly lower before finance on my appraisal.
Thank you.
That's helpful.
All right.
Yeah.
So, bearing in mind that in the column there in the table 2, Mr Bowne's table 2, THV position,
net valuation 92 .8, as you explained, is still the same.
The financial difference different than the 3 .688 in there?
Is that any different?
Sorry, which 3 .88?
Second box or row says finance rate, it's a little narrow one, 9%, 7%, 3 ,688 ,284.
That's expressive of the difference between you.
So that hasn't been calculated.
But I think it must be different from what you said.
There will be a minor difference because there is a change in the cash flow appraisal.
There will be a minor difference.
So within that difference, overall difference that we've identified in my change of residual value,
there will be, some of that will be proportionate to the finance costs
because if you increase the construction programme, you will increase your finance costs.
So I think just for your...
So perhaps the finance rate difference will actually be reduced, the financial difference between...
It does. 3, 4, 9, 8, 8, 7, 8 for your note to cheque.
3 4 9 8 8 7 8 do you want me to cheque it right now?
No, but just for just for that's that's what it is just for your for your notion if you want to cheque it afterwards
Oh by all means do okay, but I'm doing I'm doing this obviously
Almost entirely for the inspectors benefit. So that's that's what that number should be
3 4 9 8 8 7 8. Okay. Thank you
So the biggest difference is even remain don't they
by considerable margin in terms of their effect
on the dispute between us, if you like,
the PBSA evaluation number one
and the finance point number two, correct?
Correct.
And the finance, sorry, the PBSA evaluation point,
if you like, or topic, you have both addressed
Three main components of that obviously the point about rents the point about costs or OpEx or overall costs and then the point about yield
So that's the structure that I'm going to use when we come to that topic in a minute
Can we just spend a moment there just go back to your
up -to -date
FEA please in your appendix one to the rebuttal
and
Just bearing it in mind. I want to ask you if we can agree
this. What this Argus appraisal is and obviously there's the equivalent version in Mr. Brown's
evidence, its main function is this isn't it, to appraise whether the appeal scheme,
which without affordable bed spaces in it, has any additional whatever word you want
to use, capacity or headroom, which could be used to fund affordable bed spaces.
Yes, we're looking at a direct let scheme with a 50 % nominations agreement and we're
comparing.
So there's a sometimes you look at a residual land value comparison in both of our appraisals,
we've got a fixed price for the land within the acquisition costs, part of the appraisal.
So my appraisal has 1 .228 million and then the residual profit value, which everyone
confined on the second page of that appraisal. So the 22 .76 million that's the residual profit
and then you compare that against the target profit and if there's a surplus or deficit
that tells you whether affordable housing is viable. That's right but it's an exercise on
that basis looking at this particular scheme isn't it? It's looking at Genesis Cinema the appeal
scheme. This scheme yes, yeah thank you. On this site obviously and including the
whole scheme, both the cinema and the PBSA. Correct. And at least some
regard when thinking about this, these appraisals needs to be given to the
Section 106 doesn't it because the Section 106 contains things to do for
for instance with the nomination of the rights agreement, isn't it?
So the section 106, I believe there are several different versions of the section 106
and depending on the outcome of this appeal, the section 106, the relevant section 106 will be applied.
So I would be quite cautious to just blindly agree to that.
Without knowing exactly which section 106 reference you're referring to.
There are matters that are covered or will be covered in due course in the Section 106 which are relevant to your appraisal.
For instance, exactly how the obligation in relation to nomination rights agreements is dealt with.
Yeah? So the Inspector would have to have regard in due course, wouldn't he, to how the Section 106 deals with the nomination rights obligation.
Yes.
It's a valuation obviously at the present day but that involves estimating costs over time, doesn't it?
And making an assessment about values and rents over time as well.
Yeah. And it's important also to understand isn't it that this envisages when it capitalises the value, a sale of the PBSA scheme to an investor.
Yeah, the assumed sale is an assumption that is made by the valuer.
Thank you. And that sale to an investor is assumed by both of you to be at practical completion of the scheme, isn't it?
It is, yes.
All right, thank you. And a number of those inputs involve not necessarily the
costs but a number of the other inputs involve knowledge, don't they, of the
specialist world of developing and running PBSA schemes? It does. And in that
respect as you tell us in both your main proof and your rebuttal, you have
relied on Cushman and Wakefield, I think?
I have used Cushman and Wakefield
to support my evaluation, yes.
Yeah, I mean, I didn't mean to imply anything
by using the word rely.
I mean, you asked them for inputs
and you've drawn on their inputs.
Yes, so I've taken their evidence into account
as well as my own.
Yes, okay, well, we'll come to the extent
to which it's Cushman and Wakefield or your evidence
as we look through the different points.
But can I ask you just to look in that connexion, please,
at your proof, your main proof of evidence.
Mr. Mello -Browning, just look at, in the hard copy,
it's page three, it's the first section of the,
sorry it's not page three, it's page two I think, page one.
Page one.
Introductory section and you've got the conflicts stuff
at the bottom and you've also got qualifications
and experience on that page, is that right?
Yes, I can see that.
And you tell us there, I think it's in 1 .6, yes, about your experience,
and you say that in that time since 2023, you have had experience including a variety of valuation types and purposes, yeah?
Yeah, do you want me to elaborate on that a little bit more?
Well, I have no, I have a specific question for you, which is this.
You haven't in your evidence indicated in your written evidence, including in your rebuttal,
any equivalent sized PBSA scheme that you have been involved in appraising while you've been at Tower Hamlets, have you?
I haven't explicitly said that, but I have reviewed it and my name is authored on several different PBSA schemes.
Several, okay. And is your work publicly available?
Yes, yes so Calcutta House for example is quite a relevant scheme because this is in Whitechapel Oldgate area.
This is slightly bigger in nature but of a similar scale and that I was the reviewer, the signed reviewer on that report.
that is still undergoing planning, but that can be made available.
That's alright, that's publicly available I think, isn't it, on the portal?
It should be, it should be, we might need to double cheque.
Okay, thank you, that's very helpful.
In terms of the work though that you did at Savills for instance when you were there,
I'm just keen to understand whether you, I mean obviously you haven't been involved yourself in funding PBSA.
PBSA, I take it, funding PBSA.
Have I been involved in funding?
I was in the capital markets team at Savills.
So in that team I was involved in build to rent,
investment and funding.
And build to rent has a lot of similar principles to PBSA.
So in valuation terms, the investment method of valuation
is applied to PBSA, build to rent and co -living.
And so the underlying principles apply in both instances.
So I have as I've mentioned that I have a variety of experience not just with PBSA
But with other living sectors and investment valuation typologies
So what you've just told us you just told the inspectors when you were at Savills you were in a team and you did
BTR but you didn't specifically do PBSA work when you were there. Is that right?
No, I was not I was not in the student valuation team at
I was in the overall division and doing valuations that included very similar principles of student
valuation.
Thank you very much.
This is similar principles.
All right.
Thank you.
Now, bearing in mind the work that you have done on this particular scheme and on Calcutta
House, you will appreciate, Ms Domeno -Browning, that when one is thinking about these appraisals
and the inputs, there are a number of actors if you like or participants in the process
whose views are relevant.
The developer, profit.
The HEI, the university, in terms of nominations and matters to do that.
And also the investor, thinking about yields and approach to ongoing costs and profitability.
And if we think about those one by one briefly, the developer here, obviously Valergenesis,
is principally interested in the risk of securing a deliverable planning commission, isn't he?
Correct.
Yeah. The HEI, the university, has a number of concerns or interests.
First of all, they are, we'll come back to this, but they're interested, aren't they, in the degree to which any of the units might be affordable?
I don't think we have that in written, I don't think I've seen supporting evidence of that fact.
So you don't, it's formed no part of your approach that universities are particularly interested in affordable units as opposed to market units, is that right?
No, I don't have any explicit reference to draw upon for that point.
Okay. Do you accept though that the universities are interested in whether there would be a nomination rights agreement which was hard as it were in a particular case because that would, as it were, lock them into underwriting or paying for the units for particular periods?
It would guarantee the university those rooms over the contractual agreement period.
It would guarantee them, but it would also impose a potential liability on them, wouldn't it?
It does, yes.
They need to let them.
It does.
That is the most common agreement in the market, is a hard nominations agreement.
Well, we'll come back to that.
We'll come back to whether that's right or not in a minute, Mr. Manobrani.
So the third part of the university's approach, can we agree this, is that they would be,
wouldn't they interested perhaps cautious if there was any hint that the
rental levels that had been anticipated were too high or they were above the
market? I'm not sure I can comment on that as I'm not a university operator.
Isn't it common sense though, don't you think a university would be particularly
cautious if they saw an appraisal which factored in rents which were above
market level? I imagine they would do their own assessment. Yes, did you not
understand the question? I do, I do understand the question I'm just not
happy to speak on behalf of the University. All right, okay, just have a look would you please at Mr.
Brown's rebuttal which I think is core document 3 .4b.
What reference? So within that PDF page 5 and the paragraph number is 1 .13.
Yes, got it. Now this is the contents of this particular paragraph I'm not sure
I'll be correct if I'm wrong but I don't know you commented on in your evidence in
chief so I just need to put a couple of points to you on this. You're aware I
know because you mentioned in your evidence that you've been working for
Tower Hamlets in relation to London plan matters you'll be aware of the impending
changes which are already having an effect on policy at the GLA level that Mr. Brown
refers to here.
You'll be aware of those?
Loosening the obligations and the more hard edge requirements.
You need to say yes just in case we're not looking at you.
You're aware of those.
And again, is it a question of you know or you don't know?
Are you able to confirm what Mr Brown puts there?
They recognise the onerous obligations
if it were to have caused a bottleneck.
It was -
He hasn't really been explicit there
in terms of what were the policy obligations before,
what are they now,
that's not made explicit in this evidence.
I just asked you about those.
And then this statement around viability
having caused a bottleneck,
higher education are less willing, where is the evidence to support that statement?
This is Mr Brown's evidence and that's why I'm asking you about it.
Do you know or not, Ms Demeli Browning, whether universities are far less willing to enter into nominations agreements
because they've lost their negotiating strength?
Not seen that evidence presented.
You don't know whether that's true or not?
I've not seen that evidence presented to me to confirm.
Mr. Brown, who's obviously, I'm sure you'd accept
an extremely experienced valuer in the field of PBSA,
isn't he?
Yeah, this is his evidence.
About what's -
You need to support your evidence.
Claims that are made such as this
need to be supported by evidence, not just your opinion.
So you don't know whether it's true or not.
You haven't asked or commented in your rebuttal
or your evidence in chief
and suggest that this is wrong, have you?
I've definitely spoken about the existence of nominations agreement in my rebuttal
which we can go to because that is an important point that myself and Mr Brown disagree on
on the whether soft nominations agreement or hard nominations agreement is more appropriate to assume.
Right, but this is the area, you've had this obviously for a couple of weeks in the rebuttal here
From his extensive experience which he speaks about in his main proof, Mr Brown knows, and
is telling the Inspector here, what the situation is with universities now in the changing policy
environment and losing their negotiation strength in relation to obligations.
I would apply caution to relying on just that statement alone without any supporting information
record.
Do you have any evidence to show that that's wrong Mr. Mello -Brown?
So I have, I do have some evidence of nominations agreements that are hard that I can point
towards within the borough so that is perhaps the reference points that I'm looking at as
well as Cushman and Wakefield's advice on the number of nominated PBSA rooms they've
looked at which are in the region of 19 ,000 and how many those are.
That's not an answer, forgive me Mr. Montgomery, that's not an answer to the question I asked
you.
The point I'm specifically asking you about is the changing situation that the universities
find themselves in and what that's meant in real terms, in practical commercial terms
for their negotiating position.
That's what's dealt with here.
You don't produce, I'll put it to you squarely, any evidence do you suggest or show that's
wrong?
No.
All right.
You do say, and here this is in your rebuttal, let's go back to your rebuttal proof please
at page 3, paragraph 4 .3.
This is under the PBSA growth assumptions bit.
4 .3.
4 .3.
It begins the published datasets.
Yes.
You say the published datasets market indices relied on by Mr. Brown fall within the category
of general market evidence while useful as contextual information and then you say then
I paraphrase they're not the same status if you like or weight as other bits of evidence.
but you acknowledge their relevance, not just their relevance, their usefulness, there's context to information there.
So are you moving on to a new point, just so I'm following the line of questioning, are you moving on to a different point to what we were just speaking about?
Yeah, I'm asking you about this paragraph in your rebuttal and whether you acknowledge, which I think you do, that the reference that Mr Brown makes to datasets
and the evidence he's collated is useful, which is what you said.
I'm just asking you to confirm that's your position.
In which context are you asking me to confirm?
Which data set are you asking me to confirm whether this statement is in agreement?
I'm just reading you, Mr Mello -Brown, your own evidence.
I appreciate that, but which published data set are you asking me whether I agree?
The ones that you're referring to, Mr Mello -Brown, it's not difficult.
The ones that you're referring to in this paragraph, you say,
the published data sets relied on by Mr Brown,
so we'll come to them in a second,
all the ones in his editings are useful you say, yeah?
That's your position.
So this is in relation to rental growth.
Specifically this section is in relation to rental growth.
So if you are asking me about questions
specifically related to PBSA,
rental growth and market indices on the market
that are applicable to PBSA rental implications, then yes, I agree with that statement.
If you're asking me to infer that statement to any other datasets, then I need to understand your rationale.
Okay, that's fair. That's fair, thank you.
Go to Mr Brown's evidence then, please, his main proof.
And go to his page 12, his section or paragraph 4 .2.
4 .2.
Page 12.
There are two 4 .2s I note.
But it's the first of the 4 .2s that I'm after.
So the CBRE screenshot.
Yeah, there's a heading backdrop, isn't there, at the beginning of section 4.
and section four begins PBSA development headwinds are currently and
forcibly numerous and harsh which makes it very difficult to deliver and then he
makes by reference to data a number of points about as it were the real world
what's going on in the market and I'm asked I want to cheque here because again
just thinking what you haven't haven't said in your rebuttal in your evidence
in chief. The first point that he draws from CBRE, you see the CBRE at 4 .2, do you see
there's a little arrow? Yes. And then at the second 4 .2 if you like at the top of
the next page, he says CBRE were of the opinion, PBSA investment values in
London went down by just under a percentage point between October 24 and
September 25. Yeah, you see that? That is what CBRE have reported. Sorry to interrupt you. If Super Prime isn't London, what is it? Is it specific parts of London? I'm reading that whole paragraph. Maybe that's a question for Mr. Brown when he's on the stand.
Yes, I think that's the right type of BSA, isn't it, rather than areas of the country.
Well, I'll ask Mr Brown rather than give evidence myself. Thank you, sir.
But it's the, yes, it's not so much that, it's the London assets bit in the point 8 that Mr Brown is referring to.
So he then tells us doesn't he Mr. Melly Browning at 4 .3 by reference to Cushman and Wakefield.
Just before you move on to that point just to note that that arrow that's pointing to London assets saw fall in values by 0 .8 % as that's an average across London.
some will have seen some rise, some will have seen some fall, that's an average.
So we have to be careful about taking a comment that's made about a regional
area that's quite large. The advice that's being given is between those two dates, in general
terms, London assets in PBSA fell by just under a percentage point. As an
average across all of London. Yeah, yeah, okay. And then at 4 .3,
Cushman of Wakefield who you've just just bear with me which which point 4 .3 3 of
James or the same same document we're in so we've just done 4 .2 and now we're
doing 4 .3 you with me have taken some form of advice from Cushman of Wakefield
said this and he gives us an extract from their market advice from the first
quarter of 2026 and he again he's one of mr. Brown's famous arrow red arrows and
He's pointing out there what Cushman and Wakefield have identified in terms of how very few there are, how poor the pipeline is in PBSA.
Do you see that?
I see that comment regarding pipeline, which is developments not yet complete.
Or not starting?
Yeah, not started.
Yeah, and he and he I don't ask you about his speculation about what's causing that
But again, you don't produce any evidence to suggest that's wrong. I think
I do not suggest no. All right
And I don't want to do this at great length because of time but can I can I deal with it this way?
Mr. Brown then gives us some evidence from again this market intelligence set of market intelligence data
about yield softening over the nine months. That's the next one top of page 14
Do you see that? So top of page 14? I see the PBSA yield
I do which I am very familiar with right and say you
Acknowledge again you do you haven't produced any evidence or said that it's not true that
PBSA yields have softened in the way that's described there. I see that this
London average, you know based on
Prime London, Greater London, Prime Regional, I see the trends that are happening.
My evidence takes account of that change but also looks at individual transactions that are relevant to Genesis Cinema
which has more weight in the RICS hierarchy of evidence which is referenced in my proof of evidence.
So we must have reference to comparable transactions and not just market indices alone.
I'm not suggesting that. It's fine. You can say that obviously. I'm not trying to stop you.
But that's not what I'm asking. That's a fair qualification.
But I'm asking about whether any of this is disputed on its own terms.
And then Mr. Brown draws attention to have a look at page 16.
I'll just go through to that one for paragraph 4 .6 and you're aware obviously from your experience who unite are
And you've seen again, I haven't heard any demur in your evidence rebuttal or your evidence in chief
So the evidence that unite
Have in relation to London have downvalued their assets
In the year to the end of June of this year by nearly 6 %
Yes, what we don't know about this report is what are the types of assets that Unite
are talking about?
Are they assets just in London?
Are they across the country?
What are the age of these assets?
Are some of these assets 20 years old?
All of these factors will have an impact on the valuation, especially when you're looking
at rental income, operational costs, whether the building is new build or not.
All of this will have an impact on how we draw conclusions from this. Yes for mr
Brown's dealt with your first point hasn't he if you read his 4 .7. They're mainly in London
Aren't they unite the vast majority of their units are in London
Are you aware of that?
Do you know that I
Can't confirm
Okay, well, mr. Brown can come back to that
Yeah
You'll see what the joint venture is called.
I believe United Group are a national...
Yeah, but you see what the joint venture which this relates to is called London Student Accommodation Vehicle.
Do you see that? LSAV.
Where's that?
In the first couple of words of paragraph 4 .7.
So I see that it's been referenced in paragraph 4 .7.
In the table, LSAV, in the unite statement.
USAF LSAV. So do we know what USAF stands for?
Well that's not the bit that Mr Brown is looking at and drawing on. He's looking at the London specific data.
Are you with me? So it's a specific London dataset, they've downgraded it, they're an extremely large PBSA operator, they've downgraded their London assets by nearly 6%.
No evidence, as I understand it, to dispute that, Mr Mello -Browning, from you.
No, I'm not disputing that, but again, we don't know the specifics of the accommodation,
the quality, the locations within London, etc.
So all of those factors do need to be considered.
All right, thank you.
And again, I don't think you have disputed, you don't dispute the cost inflation that's been taking place.
Mr. Brown deals with this at 4 .8.
4 .8.
In parallel, building cost information service all
in tender price, build costs continue to grow at 5%.
Yeah.
Yes, I don't dispute those figures.
Okay. And finally, if you go please to his page,
just over the page to page 18.
18?
Yeah, paragraph, got paragraph 4 .9 and 4 .10 on it.
You'll see that he identifies and again, it's no surprise given the point about general cost inflation
The opex ownership costs have also risen
Yeah
Does he give an indication as to which time period he's talking about in terms of risen just just generally I think
Yeah, I mean he's obviously mr. Mellow Browning talking about the relevant last few years that he's we say obviously
but it's not explicit.
Well, if you look at 4 .8, Mr Mello Browner,
if you look at 4 .8, he's talking there about the BCIS figures
in the period since the first quarter of...
The BCIS and OPEX are different metrics.
I'm answering your question, which is a first for me,
so just bear with me.
The first quarter of 2025, BCIS, and then you'll
see what Mr Brown says.
OPEX have risen due to general inflation and are part linked to BCIS costs you see.
So he draws a connexion rightly doesn't he between the two.
I'm not sure I actually agree with that connexion between material and labour and OPEX assumptions.
I can understand BCIS being applied to construction costs using material and labour,
but operational costs yes there is a there might be some slight cost due to the cost to do with maintenance and repairs,
but all the other costs within an operational budget also include utilities, staffing,
all of those, all of those, yeah utility, all of these costs are not necessarily linked to material
and labour. BCIS is a specific build cost information service specifically linked to
construction costs, there is also CPI for inflation to look at consumer prices.
Mr Mello -Browning, I don't want to cut you off, but you're not disputing, I take it,
that OPEX costs have risen in the past couple of years, are you?
You haven't given any evidence to that effect, so are you disputing that?
I would quite like to refer back to my evidence because we're looking a lot at James L Brown's evidence
but I would actually like to point the inspector to...
By all means, but show me the evidence where you should say or demonstrate by reference to some evidence
that the OPEX costs have gone down or stayed the same.
In my, in my, in my appraisal, sorry, in my proof of evidence, if we turn to Appendix 4,
which is, in your main proof that is, my main proof of evidence, Appendix 4, yes.
We can see that Cushman and Wakefield talks, sorry is everyone with us?
or okay so section four talks about OPEX so pages three and four and it talks
about I think there's also section four and then five inflationary growth on OPEX
so it talks about the pressure the pressure on OPEX yeah but it doesn't
necessarily mean that the OPEX will inflate in line with inflation because
operators will look to create efficiencies within their assets so if
there are ways to make the operational expenditure more efficient
they will look at ways to do that so it won't necessarily elevate in line with
inflation and that's made explicit in Cushman and Wakefield's evidence.
I'll ask you about directly in line with inflation.
You've taken us to the paragraph where your advisors have identified the very point that
I'm putting to you.
This section five, inflationary growth and operating expenditure, is the reason that
you yourself have increased your OPEX costs.
They understand the inflationary pressures under OPEX, but what I'm saying is it's not
necessarily, you don't take BCIS and just apply a percentage to it.
I didn't say that.
I just wanted to try and help you inspect as much as possible Mr. Van O 'Brien by keeping to the point that I'm asking about
This is the evidence that you've relied on you yourself have increased haven't you through the course of this your opex costs that you've taken into account?
so
My opex costs have not actually
Increased Cushman and Wakefield's opex costs have increased. They're the ones that you bear in mind you rely on them
That's why you're showing us this very document. You've just taken this to
That's where you get your OPEX figures from, isn't it?
Yes.
Right, and they've put them up, 3 ,000, now 4 ,000.
My simple point was, parts of these headwinds are the fact that OPEX costs are going up, and that's correct, isn't it?
What's great, sorry?
That OPEX costs are subject to inflationary pressures and increasing, as your advisors themselves say.
question.
There is some pressure on OPEX operational
expenditure, whether there are some pressures in
terms of increasing but also energy efficiency,
procurement savings, technological and
operational efficiencies alongside rental growth to
capture the inflationary OPEX environment.
As mentioned in that first paragraph of Section 5.
What is the answer to my question, Mr Manning?
I think it is, you know, I think it is a question
I'm trying to be as straightforward and simple as possible with you.
May I ask a question?
Please do, sir.
Can you point to me any explicit evidence that you've provided that OpEx is either staying
the same or going down as opposed to increasing?
Staying the same or going down.
Or any evidence that contradicts or Cushman's evidence?
So just to help you because at the moment the questions is your own, not your own, it's
the evidence you've relied upon in part.
So just it just helps putting it into context because my previous assumption of 4000 application
I felt was overly generous, I thought was too high.
So if I was taking an actual operational expenditure
of what I thought it would have been lower,
so then my operational expenditure would have increased,
but because I went higher than what professionally
I thought was reasonable in order to meet an agreement,
that is why for the direct left option,
the operational expenditure has stayed the same.
So it can't it's difficult to answer without putting that context in there because in
professional terms
Yes, I understand the pressures on operational expenditure and and the increases but we have to understand that
Application stage when I adopted four thousand I was explicit that I was going beyond what I felt was reasonable at that time
Because there was evidence to suggest low operational budgets and we can have go back
to that evidence which shows operational budgets of below 4000.
But why did you do that because there's lots and lots of points of disagreement here so.
Why did I go against my view?
In order to in order to meet an agreement to in viability is very common.
But you're not agree.
above that you go above your assumptions or below your assumptions in order to
agree with the parties so that's that's why I did it it's very common in
viability to go against your professional judgement in order to meet
meet those differences.
Does that make sense? No I understand what you're saying.
I will leave it there.
Mr Warren has it further.
Cushman and Wakefield,
their advice was £3000 at the time.
They have now increased that to £4000.
Whereas I went against their advice,
against the evidence that was presented to me,
and went to £4000 knowing that there was
some headroom in that figure,
knowing that it was above the evidence
that I was looking at,
in order to try and reach an agreement
now that time has passed and the figure now has actually reached 4 ,000, it doesn't mean I should adjust it again,
because that adjustment takes into account that I was already above the evidence.
Okay, yeah. Well, so thank you. I just let me preface this next question with this comment.
I'm not interested here, just so you understand the context, in what may or may not be good practise
or actually happened in terms of trying to reach agreement on things.
I'm trying to deal with what the actual evidence is, okay?
That's why I'm asking about what Cushman Wakefield advised you.
I'll just come back to the simple point.
It's the last one in this series of points about the market.
It's right, isn't it, that there has been inflationary pressure
on operating costs?
Yeah, there has, yeah.
All right.
So I want to turn to the to the GDV topic in the light of all of that background if you like and market the market position.
The cinema GDV not in dispute I think in as we sit here today between you, you're both using a figure of four and a half million pounds aren't you for the revenue from the cinema.
gross value of the cinema.
And I don't think that's always been the case, has it?
So why have you now agreed 4 .5?
So at application stage, we procured advice from Cushman
and Wakefield, who provide evaluation of the cinema.
That was slightly lower at 4 .25.
million and then looking at appeal stages very common for viability
assessments to make a judgement as to which areas can we agree on which areas
can we disagree on so various items which have been made explicit for
example legal costs I increase my legal and for the cinema I agreed that
valuation and the reason why I agreed that valuation principally for the local
planning authority, it was going to cost a considerable amount of money to provide a
revaluation of the cinema because that was based on when you get an updated report by
a professional market participant, that incurs a fee.
So if I could avoid the fees for the local authority, that would be saving public money.
So I thought that it would be appropriate to agree the valuation with James L Brown,
especially considering there was a very narrow area of disagreement between the parties of
250 ,000 gross valuation.
Okay, so it wasn't that you adjusted to 4 .5, not on the basis of any actual evidence, but
to save costs with the council.
Well just to clarify, just to clarify, the difference in valuation is quite small that
I thought that that would be appropriate to agree and not to spend additional costs on
procuring an updated valuation report.
I thought that I would be being helpful in narrowing the areas of disagreement.
I think the answer was just yes to that, Mr Mello -Browning.
I was just repeating what you just said to us.
I think I'm allowed to clarify the additional context.
Yeah, okay, that's fine.
But I'm trying to get to the bottom you see of what the evidence shows and you've explained why you went from the 3 .96 that we had from Kishwin and Wakefield before to the 4 .5.
It was too small a gap to argue about if you like and you didn't want to spend the money on it, that's fine.
The cost of the cinema itself is in the region isn't it of £16 million.
Can we go to the reference of that please?
Yeah sure. It's Core Document 9 .1.
So just allow me to bring that up.
And when you're there, PDF page 25.
When you're on page 25.
25.
So does it start with 11 .5 on page 25?
It starts.
It's a PDF, page 25.
It's got build costs in it.
Build cost 13.
13, you see.
This is obviously the letter from Mr. Brown in March, 2025.
And at 13 .4 is the figure, which I don't understand
has ever been challenged by the council.
The cost of the cinema is 16 .024 million pounds.
I would actually quite like to go to my own evidence, WW's review of that.
Are you disputing it?
If I can take the inspector there before commenting on that value that would be really helpful.
That's fine, but do you know whether you're disputing it or not?
I first want to go there please.
You don't know whether you're disputing it or not?
I think I'm okay to...
You're entitled to take us wherever you want but again, we're both and principally me,
going to be criticised if we overrun horribly in this cross -examination, we're trying to
do things speedily.
This isn't an issue, this has not been an issue between us.
This is not a memory test and I would like to reconfirm with WW's assessment of the build
cost because I did not make that report of the construction costs.
So if we can turn to that core document reference.
Look at it by all means Mr Bellow -Browning and in five minutes time we'll come back to
point that it's never been disputed but go on then remind yourself what it says.
Yeah I do have quite a relevant point to make so let's go to that evidence which
in my proof of evidence I just need to find the relevant appendices.
So in my proof of evidence, WW's report is available from PDF page 95 I believe.
So that's their first document, is it, rather than what's called the proof of evidence.
So at the moment I don't think it matters.
I'm just asking where you're taking it.
So one second, I'm just finding the exact page reference needed.
PDF page 108 in that first document.
We go to PDF page 109, the detailed breakdown.
108's got the figure in.
Review of developers viability cost plan.
I would like us to go to 109.
So can you see there's a detailed table, detailed breakdown.
So in this detailed breakdown we have we have the sort of different structures
the cost elements and we can see the first the first element relates to the
basement. So what the point I want to make basically is that the
appellant is attributing the whole cinema cost, the whole of the cost of the cinema
to a proportion of the development which the most expensive part is the
structural works which is the basement. That is the most expensive part of that
16 million. If you were to actually look at other student developments you would
see that other student developments also have basement excavation works. So is it
really appropriate to apply the structural basement excavation to only the cinema when
other PBSA developments also have basement excavation works.
If we are to look at just the fit -out costs of the cinema in isolation, this document
tells you how much the fit -out costs are of the cinema.
And if you look at just the fit -out costs of the cinema, that doesn't make the – when
you look at the fit -out cost versus value, that actually looks a lot more comparable
than taking the structural works of the building.
I'm not sure how much it helps me to consider theoretical alternative developments
which might or might not have basements.
What I really want to know is, is it agreed that the cinema costs $16 million?
I think it's not, I don't think it's, it's,
I don't think it's appropriate to look at just that headline
because in order to build, in order to construct a building,
you need to undertake structural works.
And undertaking the basement, which is attributable to the cinema,
doesn't in fact mean that if it was just PBSA,
that they wouldn't also excavate the basement.
So to just take that whole cost to just the cinema,
I don't think is necessarily that transparent or reliable.
So I would I would place some caution basically
Just go to the previous page please. Mr. Mello Browning
This is one of those
Moments where it takes us a long time to reach something that we should have come to immediately
This is Ward Williams's summary table
Review of development viability cost plan and they have got there's a broad field section and there's a ward Williams section
So your advisors and they've got a column for the cost of the cinema and the cost of 16 .942 million.
Do you see?
Based on Broadfield's assessment.
Their assessment.
Yes but their assessment is based on Broadfield.
How Broadfield have accounted for the different elements of the cinema.
Ward -Williams review is based on their assessment.
I'm providing my interpretation that putting all of the structural basement works onto the cinema to try and
Justify that the cinemas not viable
I don't think is appropriate because other PBSA developments also have basement excavation works how it's been
Presented in this document looks that way. Yes, but I'm providing extra additional clarity so that is any of that in your written evidence
No
So can we just agree that what the inspector sees in the Ward -Williams cost column for
the cinema in their document is £16 .9 million?
Yes.
Yes, thank you.
All right.
I'm going to turn to the PBSA GDB, but before I do, I just obviously put a marker down that
My time estimate is is plainly not going to be met and I I
Won't say why but let's try together
Mr. Mello Browning to stick to the question and to help the inspector by answering the question that I'm asking in each case, okay
Because otherwise we'll both get into trouble with him. So PBSA
Gdv, I put you for rents opex and yield the rents first of all
Mr. Brown in his evidence has evidence that he draws on doesn't he about the
gross rents and his if you want a reference I can give it to you it's in
his proof yes page 23 PDF page 23 I can't promise it's PDF page 23 forgive me
They are the same.
They are the same, thank you.
In that case.
So, sorry, is this in the proof of evidence or the...
Proof of evidence.
Sorry.
Proof of evidence.
Page 23, paragraph 6 .1 .1.
6 .1 .1.
Proof of evidence 23, 6 .1 .1.
Yep.
His PBSA valuation is 81 .8 million, which breaks down to 281 ,000 odd a bedroom.
Yeah.
Yes.
And by contrast yours is three hundred and seventeen thousand five hundred and ninety four pounds per bedroom, isn't it?
Correct yes, okay. Thank you
All right, mr. Brown bases his
assessment of those
Numbers his valuation and his breakdown per bedroom on some comparable evidence
Which part of which he first provided to you and to the council in March of 2025?
Is that right?
He did, yep.
Right.
And he also supplemented it in September of this year with some research as it were just
before or just around the time when the new academic year was starting, 26, 27.
Correct?
Yes.
So for your notes, so the first one of those is called document 9 .1, the second one is
called document 9 .15.
Those pieces of evidence, the comparable evidence that he draws on in 9 .1 and the evidence in
9 .15 are represent and they are evidence of actual rents.
It's been a while since I've looked at James Brown's comparables from his initial FBA.
Could we find the reference where he explicitly writes about the rental values of the comparables?
Can we just go to that page?
Let me just ask the question again.
If you can't answer this then we will go to that.
But the evidence that he gives is based on actual rents, isn't it, that he's researched?
I would like to go to the reference in 9 .1 just so I can see it.
Okay, so go first of all, Mr. Mello Browning to call document 9 .1
And in
In his gross rents section section 10 it begins on page 13 1 3 of 136
There's a little table and then at 10 .1 .2
He says this is based on consideration of the following direct. Let gross asking rent comparables and then he sets them out
Yeah, yes. So my question was
Let me cast the question again. Mr. Bradley. My question was these are actual rents on they
So he the way he references these rents are from a value so from the minimum value
So he doesn't actually give a range which there there are a range of these values
he gives from this value which from a valuation perspective doesn't actually provide much
clarity as to what the asking rents or achieve rents are.
It tells you what the minimum threshold is that the rents start from that value but it
does not give you what the medium, the high, the low, the range is.
So I would say that that evidence is not very strong in my view.
We'll see what the other evidence is in front of the Inspector in relation to that point in the moment.
But there we are, we've got Mr Brown's evidence, so this is back in 2025, looking at those four PBSA schemes,
some of which are very close by obviously, Pacific Court, others in the general area,
and he's given us what they were being identified as at that point.
So for instance, Pacific Court studio from £480 per week.
That's his reported figure.
Thank you.
You rely, don't you, on Cushman and Wakefield,
as we said earlier on for this.
If you can't remember, let's have a look at your proof.
Page 13, page 13 of your main proof.
I can't remember, are the PDF pages the same in this one as well?
I've gone to PDF page 13 for the gross development value PBSA section.
So did you mean actual 13 or PDF 13?
I think I mean actual 13.
5 .14.
Right at the foot of the page it is 5 .14.
My rental assumptions informed by a specialist advisor, Christian Wakefield, supported by
a substantial body of comparable evidence from East London PBSA schemes and then you
refer to Appendix 2. And those bits of evidence in your Appendix 2 are the same kind of evidence
aren't they, as Mr Brown is referring to in his?
They're sorry, I missed that.
They're the same kind of evidence as Mr Brown is referring to in his evidence.
Well the differences are there is quite a I think James L Brown has referred to
four different comparables I here have referred to I can't count that I didn't
say no more than ten and then the rental the then explicit references that I have
the rents per week give a give a range rather than just saying from this date
it also gives more more information in terms of the number of beds the age etc
the term so there's different information so some of those
comparables are the same. My question Mr. Miller -Browning was it's the same kind of evidence so you
haven't produced for instance evidence, Cushman and Wakefield haven't produced
evidence about how much you know John Smith was paying it's the same kind of
evidence isn't it range evidence from the operators of those schemes. Yeah when
you're talking about asking prices we're both looking at asking prices on
the website for PBSA operators have advertised.
Okay, thank you.
And Mr. Brown's evidence, so I don't know, do you still have Core Document 9 .1 open?
I do.
Yeah.
The one which has got Pacific Court and East Court and so on.
I do.
Contained in it.
If one looks at those, let's take the en -suites for instance, I'll just take that example.
that category of units, the point that Mr Brown is making here, or one of the points
he's making here is that the rates here, the values that are shown, the prices that are
shown if you like, are lower than the £283 a week that you have taken into account on
the basis of the Cushman and Wakefield advice.
That makes sense because his are based on the from, the minimum value, the minimum rental
value rather than they're not actually explicitly giving the reign and they're just giving you
the lower value so that does make sense.
They say from don't they?
And the Cushman's, I don't know if the inspector can read it as well as we can, the Cushman's
range starts at the bottom and goes up to the top.
Yeah?
So what Mr Brown's evidence shows is that the figures that are being advertised are
lower than the 383 is the relevant figure isn't it Francois that you're taking into
account in your evidence. So when you say 383 yes remember that's the advice that
you provided in your letter of the 9th of September core document 9 .19 in
relation to this category of unit do we have to go through every single
reference this is the 9 .19 yeah do you remember this it was relatively recently
9th of September you wrote a letter it had gross rents in the en -suite rents
for 383 pounds. I do need some time to just get that reference.
So do you mean this statement of common ground evidence 9 .90 that's 9 .19 on my CD.
I don't think it's a statement of common ground, it's the letter of the 9th of September, so
I think you're misreading the title.
It's called the document title is Development Viability Statement of Common Ground Evidence
without Prejudice Letter.
Yeah, absolutely, Development Viability Statement of Common Ground Evidence without Prejudice
Letter, yeah exactly.
So it's not the statement of common ground, it's the letter, isn't it, from you to Miss
Cameron 9th of September and it contains various bits of as I understand it
evidence that you rely on and we can see what the rental evidence table says
because it's content that's where we've got the number. Why are we looking at
this specific letter as opposed to the most recent proof of evidence? Well
because this is where the number comes from that you then wrote up in your
I'm taking you to the actual data that you provided.
The comparable table, this is an out of date letter and then the comparable table within
my proof of evidence.
If you're looking at this table then…
I think here we're just trying to confirm that the number that Mr. Warren's alleging
you've used is the number you've used for the rents.
I didn't understand it was disputed.
Could we take it as not disputed unless obviously you've got…
The three, three nine nine.
The space can interject if it's wrong.
Three nine nine, or I'm just confused as to which.
I think it was three eight, three eight, three eight.
Three eight three.
I'm just trying to find that reference.
It might help to flow a question if
we could occasionally assume something is correct.
And there's some explicitly noted notes.
When it's viability in numbers, it feels a bit,
I kind of want to look at the evidence rather than agreeing to something. I do understand
where you're coming from, but you know
3 -8 -3 doesn't mean anything in terms of off the top of my head, so I'd rather see it on paper.
We can rely on Mr Exjected if he makes a response.
Set something which he doesn't.
Yes, it would also be helpful to, while I follow, I don't know if it's 383 by heart and I wouldn't know exactly where that's coming from.
But I agree in principle that obviously if Mr Warren is saying something that I know to be untrue I will interject.
But right now I'm not sure where the ratio is from.
But I don't think Mr Warren has plugged it from Vinair.
So the question I was asking Mr Miller -Browning was about the number that you've assumed for en -suites
drawn from the comparable evidence that you have provided.
I don't mind whether you refer to the underlying letter
or to your proof, but show me where that number is
if it's not 383, because that's the figure
that we've been working to.
It's in the rebuttal from Mr. Brown.
So I don't want to spend hours doing a kind of
archeological dig through the evidence.
this is the relevant figure that can you actually point to where 383 is
yeah I'm just I'm trying to help you with that mr. Mellow Browning but this
I'll put it a different way while we find the reference, but what is your number?
So what is the valuation?
The valuation that you're ascribing to an en suite bathroom as the gross rent.
So that's the appendix to the main point.
Well it's in a separate CD.
It's also in the proof.
Under proof.
Yeah, that's the one from September.
But I'm just finding the beginning of the document.
Yeah. So I think it's appendix three to your, to Mellow Browning's evidence.
To my evidence, appendix three.
Appendix 3, even though the title sheet says BOV 2025, the document actually that you produced
properly I think is the September 2026, the latest one.
The September 2026, yep.
That's the one Mr Brown's referring us to.
And then within it is this one here, isn't it?
So here are the rents.
Is this page 67 of the PDF?
Yeah, so I'm using a hard copy, 71, 70, 69, I think so, yeah.
It's the one it's got brokers opinion of recent rental pricing and then there's tables that look like this with the scenarios on
Scenario one direct less. I'm looking at scenario two, obviously the noms at market level
So the investment pricing scenario to you see that
rent part per week 26 27
Brokers opinion of rental pricing.
I think we're on the right page.
So within that table do you see cluster 2 to 4, cluster 5 to 6?
So not the studios, the en suites.
375 and 385 and the average of those is the 383 that we're looking at.
That's where that figure comes from.
Right, so 375, 385.
Okay, so anyway this is the evidence that you're relying on because it comes, this is the evidence from Cushman and Wakefield provided in this table in the September 2026.
Bov or Bob?
Okay, thank you.
So when we have a look at the rents that we have in Mr Brown's evidence, the Inspector,
let me put it this way, I'm sure we can agree this, will be able to compare, won't he, the
rents that are in Mr Brown's evidence with the rents that are shown in this table?
He will be able to compare that and he'll also be able to see the commentary, the detailed
commentary that's provided within Cushman and Wakefield's report as to why the benchmarks,
certain comparables are, like I said it depends on each comparable specifically as to how much
weight that you give it according to the hierarchy of evidence. So just stay with that document though
Mr. Mello Browning, the Cushman Wakefield document in this appendix.
There's a title sheet and then there's an introduction.
Actually I've got a page which has got appendix three September 2025 on it.
Do you have that kind of divider sheet, introduction sheet?
September 2025.
Yeah that's right, it's a mistake but I'm just looking at you say appendix three, it's
this, it's just before the document.
Page 59, PDF.
PDF, page 59.
Of my proof of evidence.
Page 51.
59.
59.
Oh, okay.
A typo.
A typo.
But there's something slightly more than a typo involved, isn't there?
because the previous one I think was called BOLV,
wasn't it Brokers Opinion of Value?
But when you look at the September 2026 document,
Cushman and Wakefield are calling it something else,
aren't they, on the next page, the first main,
you know, the front cover if you like of their document.
Brokers Opinion of Pricing is now called, isn't it?
Are you inferring that there's a difference
between Brokers Opinion of Pricing
and Brokers Opinion of Value?
It's so unhelpful. It's so unhelpful Mr. Mello -Browning. It really is. It's so unhelpful.
Just answer the question please.
So previously their documents were called Brokers' Opinion of Value, weren't they?
And this is called Brokers' Opinion of Pricing, correct?
That sounds correct.
Yes. And if you look at the introductory section you can see why, can't you?
It's called Introduction Brokers Opinion of Pricing.
And it says, what is, do you see the second section?
What is a broker's opinion of pricing?
It says, a broker's opinion of pricing
is an informal market opinion
prepared for a specific purpose.
Differs from a red book valuation,
was a formal valuation.
A broker's opinion of pricing is an agent's
professional opinion of what a property
could reasonably achieve in the market.
Yeah?
So it's a piece of, it's a number or a set of numbers which as they say indicates market
pricing, correct?
Yes.
Right, it's not a valuation, either a red book valuation or any kind of valuation, it's
expressed in something like pricing.
It's an informal market appraisal which is an informal valuation.
No, it's not what it says, it doesn't describe itself as a valuation, it says in terms, no
doubt they thought very carefully about this.
It is commonly used to provide an informed indication of market pricing.
If I could just help the inspector.
As I mentioned in the examination in chief, this is a market appraisal.
It is very, very common in viability assessments.
I'm sure ROC planning have also relied on agents' opinion of value or pricing to inform
their viability assessments.
It is extremely common.
This is a public inquiry and I'm very shocked that this argument is being made on this document
in particular.
Now, if I can take you to references within the core document to very similar agents'
opinion of pricing then you'll be able to see that this is a very common
approach to have evidence relied upon in a specialist area so I will take oh I
think it will be helpful I think it will be helpful I'm not sure I'm not sure it
will be Mr. L. A. Browning. Let's ask the inspector whether sorry so to put you on
the spot would you find that?
whether or not you are shocked, Mr Mello -Browning, Mr Brown has said, hasn't he, for instance,
in his communications with the authority, that the trouble with this type of approach
is that it is an agent's pricing document and things don't necessarily sell for the
price at which agents put them on the market. I understand his view, his opinion.
I would like to qualify what other viability professionals
have done in core documents that I have referenced to show that it is very much
appropriate to rely on this evidence and I'm very shocked that this argument is
being put forward. Are you? Okay well that's fine but it is being put forward.
you've seen it. Can I just point the inspector to the references to just
illustrate this point because it's very important as a public inquiry that we're
all on the same page. So my note so far is there is a difference between pricing
evaluation and I'm now trying to establish if it matters to what extent.
Yes. And in between I think you answered, though let's cheque shall we, my question
which was, as Mr Brown says, the difficulty with pricing by agents is that things don't necessarily sell at the price that they think should be put on them at the beginning.
That's true, isn't it?
Cushman and Wakefield knew the purpose of this instruction.
They are not selling Genesis Cinema.
They are not basing this on an exercise to sell Genesis Cinema.
They know that the purpose of this valuation this pricing is a market appraisal for planning purposes for this inquiry
There's no benefit to them to
Change their opinion of valuation based on what they think they could
Sell that asset for because they are not selling the asset and if I can take you to
Again I'm still like my principle duty here is to the inspectors as yours
as well.
Okay, so I'm trying to assist the inspector.
And my question was, and I'll ask it for the third time,
do you agree with the point that Mr. Brown makes about agents' pricing,
which is that things often don't sell for the prices that agents put on them in the market?
That's correct, isn't it?
Am I allowed to qualify my answer?
Well, you give it first and then qualify it.
So it is true that things don't always transact for what they will transact for as an asking
price. But I would like to qualify the weight to be given to Cushman and Wakefield's evidence
and by doing that I'd like to turn to core documents references, CD9 .28. And there's
open also CD 9 .25.
Which one are we going to?
I'd like us to open a few documents.
Okay. So if we go to CD 9 .28, which PDF page,
PDF page 169.
Just to give this some context, this is an FBA valuation done on behalf of the applicant
by Savills for Calcutta House, which is a development within the borough very close
in location to Whitechapel.
we can see that this is a letter by Seville's in -house student PBSA team and some of the
caveats written when you look at this report.
So for example, it says, we understand you've requested this advice for feasibility purposes.
Please note the numbers are subject to inspection on a non -reliance basis.
And then it also says this does not substitute a valuation undertaken in accordance with the RICS red book now in your own time
You can have a look at the the caveats because I think what's important is rather than getting hung up on
Pricing and value. It's actually looking at the small print to these
valuation reports and the point that I'm trying to make is that it is
here they have got Saville's an
on behalf of the client of the applicant in order to support
their PBSA evaluation.
And then if we turn to CD9 .25 and we go to PDF page 77,
sorry, so that's, yeah, PDF page 77, it says JLL's Brokers
opinion of value.
And here again we have another PBSA development archway where JLL have acted on behalf, Savills
have instructed JLL to do an opinion of value of pricing to look at this student development
and to appraise it and then they've relied on that value.
So in both instances Savills as a viability expert have used an agent to inform their
PBSA valuation and that's on the applicant side and there are
multiple other references that I could give you of how this is a
completely legitimate
exercise in viability and valuation and this is why I'm shocked that as the local authority by us
providing this evidence from Cushman in paying for this
financial report for this pricing
why this argument is being taken against us,
when it is so common in the industry
to rely on agents opinion of value,
not only in student accommodation,
but across lots of different sectors and values.
So that is the point that I want to make
in terms of when you're considering
the weight to be attached to Cushman and Wakefield's,
do look at the core document references
and do see what other market participants are doing
and what kind of small print valuation it says in their caveats,
because it will be very similar, and it's better to look at that
rather than the headline value or pricing.
Right, thank you. Thank you very much for that.
Those documents that you've shown us,
I think they were the ones that went up on the website last night, weren't they?
We hadn't seen those before. I'm not complaining about that.
But they're not evidence that a public inquiry of value, Mr Mallow -Browning.
that's one of the reasons why I'm allowed and am probing the weight that
can be given to your evidence, the evidence that you rely on. And what
I've pointed out to you, and I think it's correct isn't it, is that originally
Cushman and Wakefield produced something called a BOV, broker's opinion of value,
and then they had seen no doubt through you Mr. Brown's initial concerns
which he expressed in writing, didn't he, in letters about the status and reliability of that work.
And then in September they produced another document which is now called something else
and says very carefully in it that this is a pricing exercise.
And I've put to you already that prices don't necessarily get borne out
and that goes to the weight of the evidence. Do you see?
I see the point that you are trying to make.
I see that Cushman and Wakefield changed the
title of their document.
So initially it was called Brokers Opinion of Value,
the same as what we have just looked at as JLL,
Brokers Opinion of Value.
They have then changed the wording of pricing.
But the reliance on that document and the intention
for that document was always known by Cushman and
Wakefield from the beginning and they have not
informed me as to why that document changed from
Pricing to value we could always qualify that if necessary. I don't think it's necessary. I understand both sides on this point. Thank you, sir
That's helpful
I'm just conscious of time. I know we're finishing at 1 today anyway. I'm over the hour. I'm sorry. Yeah
Yes, I feel I would do need a break essentially about now really
I hesitate to say this but any time I think would be welcome so now is just as good as
ever.
Thank you.
So should we have a break, come back at ten past twelve.
Do you think you're finished today?
Not if we sat until six o 'clock at this rate so no.
Okay well we do have some scope in the programme obviously if you'd be sitting tomorrow as
well so.
We're going to have to I think.
I'm I'm also working on another public inquiry. So it's quite difficult with my availability to have a
Undesignated time I do need to know exactly what tomorrow
tomorrow morning
Morning, I have asked for all witnesses to be available today after the experience
Right. So just tomorrow morning. Well, it's very I need to be very like
Depends on how long your answers are Mr Mello Browning to be absolutely honest with you.
It could be tomorrow afternoon if you don't answer any of my questions the first or second
time I answer.
I mean you've started to sit in this inquiry.
I'd expect you to sit until you've finished the cross -examination which should be tomorrow
morning.
It should be tomorrow morning.
But it's not ready for me to say.
When are you expected on the other inquiry?
I'm giving a statement of case on the other inquiry and it really requires my inquiry.
This has to take priority.
You will have to sit until you are finished.
Okay.
So it's 5 to 12.
Shall we come back at 10 past 12?
Is that okay, everybody?
Thank you, sir.
Okay, thank you.
The inquiry is adjourned.
Thank you.
Resumed.
Should we wait for Mr Cameron to return?
I don't know.
It's okay.
We can proceed.
Or Mr Brown.
Indeed.
No, it's okay.
OK, I can start.
Thank you very much.
Right.
Mr Medelbranding, we were, we spent a few minutes talking about the BOP in your appendix
3 and now I'm going to move, just so that you understand, I'm going to move to another
point, a separate and different point and I want to ask you about what's been assumed
for the nomination rights agreement.
So first of all, I'll take my courage in my hands and suggest to you that it's agreed,
isn't it, that it is the case that Cushman and Wakefield and you assume that there will
be a hard nominations agreement in place in this scheme for the purpose of the agreement.
Thank you.
All right.
And that's not all of it.
Obviously that's of the relevant just over 50 % of the units.
Yes.
146 rooms.
Yes. Thank you.
All right.
And again, I do this as quickly as I can.
But if you go please to Mr. Brown's rebuttal, that's called document 3 .4b, Mr. Brown's rebuttal.
I'm in the rebuttal.
And go in it please to PDF page 12 of 34.
It starts with the assumption that hard nominations agree with the list.
That's it.
Sorry, just forgive me, Mr. de Benobrenning, I'm just slightly struggling with my PDF opening.
Okay. So the 2 .1 .4, just want to make sure that we have the whole section.
Are you with me at the beginning of that paragraph, which begins leaving aside ODMB's, etc.
That bit there.
Have you got that paragraph?
Because the numbered, the lettered paragraphs obviously are all part of a point that Mr Brown is making. Do you see that?
Sorry, are you pointing me to a specific section?
Not yet, I just wanted to make sure you started at 2 .1 .4, yeah? You've got that paragraph.
Sorry, no, I was in James R Brown's rebuttal.
Yeah, that's where I am as well.
So, his rebuttal, paragraph 2 .1 .4.
It's the page above if that helps.
Sorry, yes, I just wanted to go back.
I realised that I was showing you the middle of a paragraph
and I wanted to make sure that you'd seen the beginning of it.
So this is all obviously a part of Mr Brown's views
about the Cushman and Wakefield derived number for GDV.
And one of the points that he makes,
the one that I'm asking about here, is it begins at C.
So let's start at B, the assumption,
and that's what I asked you about a moment ago,
that a hard nomination agreement exists,
is likely to cause Cushman Wakefield
to assume a lower opex cost than they should.
Come back to that in a second.
And C, the assumption that a hard nominations agreement
exists is likely to cause them to assume
a rent capitalization yield which is too low,
so that's about yield, I'll come back to that.
And then there's a point about the 45 week period.
So can I just ask you about that?
So point sub paragraph D, are you with me?
Cushman and Wakefield's assumed hard nominations agreement annual period of 45 weeks is unrealistic he says.
Are you with me?
I can see that.
Yeah, okay.
Now on this, this is a point isn't it about how much revenue is being apportioned if you like between the term,
the main student let period and any holiday rents.
and the holiday rents are less obviously they're lower aren't they than the student rents?
Lower because the occupancy is 50 % rather than 100%.
Exactly and so it matters again to some degree, I won't go into the details, but it matters to some degree to the out turn in numerical terms.
How many weeks are in which category? How many student weeks and how many holiday weeks?
It matters to get that correct yes.
That's right okay.
But just to add to that, I think in Cushman and Wakefield's evidence, we can see if we
go to appendix four of my proof of evidence, they do mention that there's section three
assessment of hard nominations agreement.
Yes.
PDF page three.
So they do sort of give a range of 43 to 45 and they adopt 45.
So there is a range, it's not a fixed number of weeks but you're right, it does make an
impact how many weeks you assume.
Yes, thank you.
And here you'll see, you've seen this I'm sure before today, Mr Brown makes the point
and I want to see whether you agree with it.
a little bit further down that longish paragraph on this point, paragraph D,
that the academic year period is defined as being no more than 38 weeks.
Do you see that?
Yes, the academic year is very different to the contractual agreement
that will be entered into with the university and the PBSA operator.
They are not the same definition, they are not the same,
they're not to be confused with each other.
Right. And then at the end of that paragraph you'll see a reference, and I'm going to take you to it, just rather than put the point to you without the reference.
Do you see at the end of that paragraph Mr Brown refers to paragraph 7 .2 .2 to 7 .2 .4 of his main proof. Do you see that?
I see the reference.
Yeah, can we go to those paragraphs please in his main proof?
So that's on hard copy page 50 and following.
Is it page 48?
Of the PDF probably.
To go by paragraph numbers if you wouldn't mind just because we're using different.
7 .2 .1.
7 .2 .2.
I note from the Cushman and Wakefield Bov.
Do you see that?
Yes. And then it was it was a table actually we looked at earlier.
The scenario two nominations at market level paragraph.
We see that we're in the middle of that table right in the middle of that page.
Tenancy length. And we've got forty five and fifty one.
Do you see that? So this is reference it says to the June 2025.
That's right. Historic historic valuation.
to I think that middle one is actually September 26th isn't it? Yes September 26th so the draught version
that was draught in the beginning of the document so we can we can... Well so anyway the
Cushman, I don't think it's hugely massive but the Cushman Wakefield document on the 9th of September
26th has just been screenshotted there and it's got certain things which is not being relied upon
in the appeal that version of the document?
I understand that but part of Mr Brown's concerns relate to how some of these things have jumped around
and why they've changed over time.
So in September we've got 45 and 51 and then on the 11th of September 2026 we've got scenario 2
and it's got cluster sum it income 5, 5 do you see that?
Five weeks is what that refers to.
Five weeks, yeah.
And Mr. Brown points out, and again, I
think this is factually correct, isn't it?
The holiday period is 12 weeks and not five.
For an academic year, the tenancy length
will be different for a nominations agreement.
So a nominations agreement will have a different tenancy
length.
In this case, it's 45 weeks compared to an academic year
which for instance would be 38 weeks.
When you say in this case, obviously we don't have a nominations agreement in this case.
Do you mean in what's been assumed by Cushman and Wakefield?
Exactly, and assumed by myself as a hard nominations agreement,
which is based on comparable evidence of other hard nominations agreements.
I understand that.
We'll come back to whether there's going to be a hard nominations agreement again in a second,
But it's the assumptions for the reasons you've given about these periods 45 and 5 if mr
So hypothetical question. Yes, if mr. Brown is right that one should be looking at a
Holiday period if you like inverted commas of 12 weeks and not five
It would have the effect which he sets out in the table 7 wouldn't it below?
Yeah, I don't agree that assumption is correct.
No, I know you don't, but that's what I'm grateful for your acknowledgement.
I haven't reviewed this table in detail because I disagreed with the assumptions.
I haven't reviewed whether the calculations are correct in this table.
Fine, that's a matter for you, Ms Domeno -Browning.
This is a table in the evidence that was exchanged duly a month ago.
So that's fine.
But are you retracting your answer a few moments ago
that if you were to say 12 rather than 5 that's what you'd get?
Are you backing away from that?
I'm just saying that I haven't looked
but we can assume that yes, there will be a difference in summer income.
Yes, we can assume that for this purpose of this question.
Yes, and obviously as Mr. Agen, I know that you have your view about the premise, if you like, of the question.
But if you do take, if one was to take that approach, as Mr Brown sets out in 7 .2 .4 and 7 .2 .5, it would have an effect wouldn't it on the GDV as it were bottom line.
In James R Brown's opinion it would have an effect on the GDV, this is not my evidence, I do not stand by this evidence, I do not agree with this evidence, so yes.
In James R Brown's opinion, yes, that's what it says.
Not quite Mr. Nometto Brown. I know that you don't agree with the 12 and the 5 point.
I understand that and we've got the debate between us about that. I've asked you about it.
What I was asking about was if one takes a 12 week holiday period and not a 5 holiday period
and applies the numbers that Mr. Brown does, those are the numbers that follow aren't they?
The ones that he sets out on that page.
I understand that there would be a difference in the gross rental value by applying a different tenancy length of
12 weeks, but I have not checked those figures because I don't think it's appropriate so
You know
Fine then no, that's that's fair if that's the factual position the answer to my question is I don't know because I haven't checked them
Correct
Correct. Thank you
All right
OK, different point. We're still all under this first heading, alas, of the, it's almost
at the end of the section I'm going to ask you about on rents, but I want to ask you
another question please about the effective nominations agreements. First of all, Mr.
Mello -Browning, is it agreed, do you agree that if you want to assume a hard nominations
agreement as Cushman and Wakefield and you do, if you assume that, then what it means
is that the investor thinking about this will know that the university would be locked in
and it would be de -risked to some degree for the investor.
Do you agree?
Yes, yes, there's consideration of that.
Yes. If you're the university, of course, it's the other way around, isn't it?
That you're locked in and it's more of a negative effect, isn't it, for the university?
You're at risk if you don't manage to let the rooms...
If you're looking at it in purely financial terms, then yes.
I am, I am, okay thank you.
Alright, it is important to look at it in financial terms isn't it because one of the reasons that Mr Brown identifies for why it's very unlikely in his view that one would end up with a hard nominations agreement
is that universities at the moment do not want to be locked in to this type of agreement for market units rather than affordable units.
That's his assumption, his evidence, not my assumption.
I won't go over what we said before, I asked you about whether you produced any evidence to dispute that in relation to any university and the answer is no, isn't it?
I do have evidence on hard nominations agreements within my appendix through of Cushman and Wakefield's report, a detailed section.
Yes, I know, but the point that Mr Brown makes, which is what I'm asking you about, are you producing any evidence to show that universities are averse these days to hard nominations agreement?
When you say these days just...
Do you remember, sorry I didn't want to go over it again, but we went over it earlier on,
there's a policy change in London that you acknowledged earlier on,
there are all the other headwinds that universities like any other organisation are facing,
and Mr Brown's evidence from being in this market is the universities are very averse,
unless there are affordable units involved to take hard nominations agreements,
and my question to you is that's what he says, you don't produce any evidence to dispute it, do you?
He says that and there's no substantiated evidence behind that statement that has been shown.
Right and at some point perhaps you do in the honour of answering the question.
You don't produce any evidence to dispute it do you? You can say what you like about Mr Brown's evidence.
This is a session where I'm testing your evidence. You don't produce any evidence to dispute it yourself do you?
To dispute the point of just...
How averse universities are to enter into hard nominations agreements without affordable units in them?
So in... I would just like to refer to my appendix 4 of my proof of evidence in section 3 assessment of hard nominations agreement.
Yes. So that's the BOP, is it? That's the Cushman and Wakefield document, yeah?
Yes.
Alright.
I'm actually on a PDF 78.
Just allow me to have a quick scan of this.
Thank you.
My reading of that section is it's your assumption, the starting point is that there is a hard
numbers agreement and then explaining what the implications are.
Yes, I'm just going to cheque my rebuttal, what I write in my rebuttal as well, just
cheque my memory because I just want to see if it's written.
So there's a section in my rebuttal proof of evidence PDF page 3, impact on
So in here it talks about nominations agreements being the most common form of constructural
obligations and it talks about the term lengths, et cetera.
I don't think in here it's included exactly how many,
how many university agreements have been agreed
with a hard nominations agreement.
Without affordable in.
That's the point I'm putting to you.
Right.
They might be prepared if they can sell them,
as it were, to their punters because they're cheap
and it helps their business.
But Mr Brown's evidence from his understanding and knowledge of the market is that universities
are very averse to locking themselves in when they don't have affordable units.
So anyway that's what you've taken us to.
You've taken us to this section 3 and the section in the Cushman and Wakefield letter
which the inspectors asked you about.
So other than those two sections you don't produce any evidence to suggest that Mr Brown
is wrong?
Not in written evidence.
So in that paragraph 3 .2 of that proof of evidence on that page 3, so 3 .2 of my rebuttal,
so it says across approximately 19 ,000 nominated PBSA beds in London and it talks about the
number of weeks assumed within the hard nominations agreement.
Yeah, I mean that's a different point.
So that just gives you the scale of the evidence being relied upon in this section?
No, well I understand what it says but it doesn't address, does it?
It's not addressed to the point that I'm asking you about which is how likely it would be for this scheme to have a hard nomination, a disagreement with no affordable in it.
It just doesn't, can't possibly deal with that.
Well Cushman and Wakefield and I have valued it on the basis that there is no affordable housing in affordable student accommodation in the development and the valuation is based on a hard nominations agreement.
Cushman and Wakefield are extremely experienced in their professional views and so they have also corroborated this with their opinion that actually a hard nominations agreement would be appropriate as direct left.
I'm sorry, they haven't done that.
They've assumed one, as you've shown us already
in their document.
They don't have any justification for it
that they set out.
If they were here as a witness,
I'd better ask them about that.
Based on their professional experience
and based on the quoted 19 ,000 nominated PBSA beds
in London, this is what the figures are based on.
They're not based on figures from, you know, from NOBA.
They're based on actual nominations agreements
in the market.
Okay, well I tell you what, let's try and short circuit this.
The evidence that you're drawing the inspectors attention to on this point, to the extent
there is any, about whether a hard nominations agreement with no affordable is likely or
not is section three of the Cushman and Wakefield letter in your appendix and your section three
in the rebuttal, is that right?
That's right.
Okay, thank you.
All right, let's see if we can get the next section done before 1.
So I'm going to move to ask you some questions about your evidence on costs of running the
second component, the OPEX costs and all -in costs of the PBSA, which goes to the overall
valuation of the PBSA units. Now can I again, it's on trepidation, can I just
identify where the two parties are on this? Mr. Brown as you know is at four
and a half thousand pounds. Including voids and bad debts which is
not a direct comparison to my value. Okay let's just try to help the inspector by
answering the question and then qualifying.
So £4 ,500 on the basis that you've just said.
Yes, that's £4 ,500 per bed per annum.
And then your figure, and again, by all means say
on what basis and the extent to which it's different,
is a little bit lower than that, I think, isn't it?
Can I just be sure about this?
Because you said something in chief
that we scratched our heads about.
Is your figure 4164 now?
Is that what, because you said 4 ,400 yesterday
at one point. So what is your figure? My figure is excluding, I think we were
talking about figures including voids but for the purposes of excluding voids
and bad debts my OPEX operational figure is three thousand seven hundred and
fifty per bed for this with a nominations agreement it would be four
thousand without a nominations agreement. Four thousand without a nominations
agreement.
And that valuation is actually closer.
If you were to include voids and bad debts, James R. Brown and I wouldn't be that far
apart if we were looking at direct let units, which I believe James R. Brown didn't change
his OPEX assumption depending on whether there was a nominations agreement or not, because
we can see from application stage to appeal stage, the appraisal did not change and the
underlying income assumptions didn't change regardless of whether there was a nominations
agreement in place or not.
So actually in terms of that valuation figure of direct units, we're not that far apart.
The difference between us is actually in the savings that I appreciate would happen with
regards to having a hard nominations agreement and also the application of a
large sinking fund. Okay we'll come to those I've already asked you about
non -screamers we'll come to sinking fund in a minute but again I just just try
and help the inspector four and a half thousand pound four thousand five hundred
pounds a year per bed space Mr. Brown your three thousand seven hundred and
Excluding voids with the voids. What is that?
Because I thought that was the 4164 I
Will just cheque whether that is made
explicit in my proof of evidence
so the opex
section
We find where that is.
OpEx section 5D.
So it starts from page 15 or 17 of the PDF.
So here I say that the quoted figure, if we were to include
voids and bad debts on paragraph 5 .25 is 3 ,980 per bed.
3 ,980, so that's apples compared with apples. 4 ,500 Mr Brown, 3 ,980 you.
Yes.
Okay, thank you, that's helpful.
Alright, I mean, yes, fine, okay, so the inspector can see what the difference is between the two.
In terms of who's we're imagining expending these costs it would be the
operator wouldn't it of the scheme these OpEx and running costs obviously
person who's running it it'd be an operator like Mizino? It would be it
would be an operator that would that would run it yeah. It would be an operator like Mizino?
Could be Mizino as one of them could be another one. Answer yes I think to the
questions to Melo Browning so an operator like Mizino the best evidence
the best evidence of how much the running costs of a PBSA scheme would be
comes from operators and comes from operators how many operators have you
included in Mr Brown's evidence?
You just got your task.
Right.
So just Mezzino.
Just Mezzino.
No, no, no, no.
I asked you a general question.
The best evidence about how much these things cost to run
comes from operators, doesn't it?
Because they're the ones who are actually suffering the cost,
spending the cost.
Best evidence.
Depends how independent and the instruction of that evidence.
Okay, subject to them being independent, okay.
Operators like Mosino, owners as well, their experience, people like Tribe, what they say.
Again, you've named two examples of market participants out of a considerable number, yes?
Yes, okay fine. I'm trying to deal with it in terms of categories and weight of evidence.
You're trying to help the inspector. So it would be run by an operator.
The best evidence of this kind of thing would come from operators or from owners, correct?
If it was independent and directly comparable to the scheme in terms of its
nature, whether it has a nominations agreement, the
specific nature of the scheme, whether it's new build, etc.
There may be disagreements in terms of operational budgets between operators.
They may not all assume the same operating budget.
Okay, thank you.
In Mr Brown's evidence, which you've seen, I'll take you to the page.
It's page 28 of his proof.
Just go to that, would you?
Page 28.
Proof of evidence.
Page 28.
Page 28.
So that's hard copy, page 28.
Forgive me if the PDF is different.
What I'm looking for is 6 .1 .16.
If you can find 6 .1 .16, that's a good...
Okay, I'll try and search 6 .1.
On page 27.
So that's where you find the paragraph reference I was trying to help you with.
So 6 .1 .16 talking about OPEX ownership cost.
Inputs.
Now, Mr. Brown's evidence, if you have a look at little point Roman 2, which is where I
started, which is on page 28, it begins, my FCA dated the 12th of March, 2025, Core Document
9 .1, which included, do you see that bit?
I do.
Okay.
An off -bex cost component build up pointing to £4 ,502 per bed per annum.
Part actual cost, part budget of the cost provided by your tribe.
Do you see that?
Yes.
Your tribe, the inspector knows this no doubt, owner.
Sorry, sorry.
Your tribe falls into one of those categories we were talking about a moment ago, don't
they?
The owners of PBSA schemes?
Yeah.
Yeah.
Okay.
which have been publicly disclosed for their operational PBSA scheme in Southwark,
Ilderton Road and Old Kent Road, I think I should say, rather than Toad,
whereupon the scheduled costs don't include major repairs etc.
In other words it's pure OPEX costs that are being identified.
Do you see that?
Yes.
And I just want to ask you a little bit further down in this account, if you like,
of the evidence that Mr Brown has assembled, we have don't we,
actual OPEX costs from H, in other words, who own tribe,
your tribe, and can you see A, B, and C,
and then there's a table setting them out?
A, B, and C.
Your tribe, South Bermondsey, Peckham, and Avonmouth House.
Yes.
So these, they're all set out in the appendices
and what Mr Brown here is doing is summarising what they say, their pure OPEX costs, their
actuals for as it were up and running stabilised schemes and they show don't they a pattern
of between £4 ,415 and £5 ,107 per bed per annum.
They do.
Right, okay.
And that's summarised in the table etc.
Yes.
Yes. And I'll just note, because we're going to come back to it in a second, at the end
of that section, just before the table five, the pure OPEX costs, if you like, are noted
not to include obviously sinking fund voids and bad debts allowances, if you like.
I see that.
Mr Brown's also included hasn't he? I'll try and deal with this relatively quickly if you scan down the rest of that section with the little Roman numerals at the beginning of the paragraph.
Evidence from EQT Exeter owners in Southwark?
That's little Roman four.
I'm looking at a table by Greystar, is it that one?
So if you just stay, we were at the top of the page 29 then there's the table with the
Your Tribe sites in it and then Little Roman 3 begins my letter dated the 6th of August,
do you see that?
I see that.
Okay but I've jumped over that one and I'm looking at Little Roman 4 which is the EQT
Exeter evidence that Mr Brown puts before us.
Their owners it's a 250 bed PBSA scheme
It's in Southwark called Great Court and he identifies obviously what that evidence shows
Significantly more than four thousand pounds per bed per annum in 2024 to 25. Do you see?
Okay
and
He then goes on to show us. I think it's pronounced Tiago. It's never than Tiago Tiago properties
limited evidence
which is a public bit of information from DP9,
who you'll know don't know, planning consultants.
And he's given us that in the appendix.
And again, that shows higher than,
well between four and a half thousand pounds
and 4 ,850, doesn't it, a year?
Yeah.
Yeah.
And I won't go through, Metzino is the next one.
And you'll see there that the Metzino evidence
that he's referring to here is an appeal scheme, appellant specific budget.
Do you see that?
So we know who Metzino are.
This bit of data which Mr. Brown's recounting here, appendix K to his proof, is Metzino
telling him and telling the inspector how much they would be budgeting on if they were
to do this particular scheme.
Is that right?
Correct.
Okay. And I think it's fair to say, isn't it, that in addition to operators and owners' evidence being best on this,
it would be at least, I'll put it, I'll creep up to this one, it would be relevant, wouldn't it, to the inspector to take into account operator evidence specifically about this scheme.
It would be relevant for him to do that.
I think in the context of, you know, it's one operator's opinion, we don't know the
relationship between that operator and the appellant, and we don't know what the instruction
was, but presuming all of those are independent, then yes, weight could be given to that specific
evidence in the context of the other references that have been made by Mr Warren in terms
of the other references and Mr Brown's proof. I would say when you're looking at these different
operational budgets just to put into context whether the schemes are new build, their locations,
their specific requirements to these operational budgets, each needs to be looked at carefully.
Right, thank you. And just in terms of Metzino, so you said give some weight to it, which I think is pretty much the same thing as I was asking you about,
which is the inspector should take the Metzino material here into account, but you're not, I think, are you suggesting on the basis of any evidence
that there is some relationship between Metzino and the appellant here, which means that less weight should be given to their evidence?
I've not looked into that, whether there's a relationship between James R Brown and Metzino
or the appellant and Metzino, I've not looked into that specifically.
So yeah, no comment on that, but I'm just saying that...
So you say, depending on, you're not saying obviously the inspector should give less weight
to the Metzino work because there's some relationship which makes it less than independent, are
you, on the basis of any evidence that you produce?
I'm saying that I don't know what the relationship is.
I think I've made that clear that I don't know.
If on the presumption that there is no existing relationship that would inform them to change
their figures.
Of course.
Yeah, okay.
Thank you very much.
And obviously if there isn't evidence of a certain thing it's quite difficult for planning
inspectors to take it into account, take something into account about which there is no evidence.
You understand that?
Yeah.
Yeah, okay.
Thank you.
All right.
So we've got a series of points that you've acknowledged, you've made your caveat about, you know, look at them in detail, etc.
And the inspectors got all of that information. I asked you about Mountsino in particular in relation to this scheme.
I wanted to come back to the point about sinking fund. So obviously everyone knows, including the inspector, what a sinking fund is.
if you are taking on and running one of these schemes, a PBSA scheme, if you are Metcino or whoever it may be,
you have to think, don't you, about the consequences over time of wear and tear to the premises.
Yes.
And some of those premises have, they've all got similar types of facilities in them, but some of them at a particular point in time are going to need more substantial work than just as it were a lick of paint, aren't they?
Do you mean over a number of years? Some will need more.
Some have M &E things, you know, trickle vents or whatever it may be, all sorts of things,
that's just an example.
There are things to do with running PBSA schemes, communals and communal areas and so on, that
may need a bit more expenditure on over time.
But you can I'm sure understand that if you are such an operator, it's prudent, isn't
I'll take it in stages prudent, you can see, to make provision for larger costs.
Not just 20 minutes before you need to spend the money, but earlier than that.
I think that it's appropriate to have an allowance for maintenance and repairs within the operational
budget but to do any large extensive repairs and works to a PBSA building sits outside
of the running, the phrase operational expenditure refers to annual operational expenditure which
is explicit, it's not a saving for some large capex work that could happen in the future.
That's my view.
That's a helpful answer, but I think the point that I need to put to you is that however
one defines OPEX, yes, whether it's more run of the mill if you like kind of stuff, it's
relevant, isn't it, whether it goes under the box or into the OPEX box or somewhere
else in the assessment, for the costs of these schemes to take into account the kind of things
that I've just been putting to you?
It is appropriate and has been demonstrated in my evidence that repairs and maintenance
have been accounted for within the operational budget.
And I can take you there if you need that reference.
Well, no, that's fine.
I'm interested in the point, I think, first of all.
So making provision for larger items, more expensive items of repair, if you like, is
something in principle that you accept operators should do.
More expensive items of repair. Can you expand on your definition?
Right, so if for instance part of the roof needs replacing or the cladding needs replacing
or the windows become non -functional on one side of the building because of weather and so on.
things that aren't just a lick of paint and a bit of carpet in the communal area
that you accept as I do you that it's prudent for an operator or owner to make
provision for those. You wouldn't expect a new build development to have these
kind of large -scale works happening so soon in the development period. You would
expect major major repairs like the ones that Miss Warren is suggesting to happen
a lot later, but there is a budget for repairs and maintenance.
You know, that budget that's been allowed for within my evidence, sometimes that budget
won't be spent, other times it will be higher or lower.
Operational budgets that are assumed in viability terms, in reality, those operational costs
are not fixed, they will change.
So some years it might be higher, some years it might be lower.
All right, listen, I just want to clarify one thing, then we'll move on on this point.
The time scale, I mean obviously I understand that you shouldn't be providing, you know, from day one for lifts to be replaced in year two.
Thanks.
The time scale that we're talking about isn't just one year or two years, is it?
What time scale of provision by operators and owners are you, do you have in mind for this exercise?
What time scale? I'm looking at it as a new build asset.
As of today's value what the operational cost would be as of today's value as an investor would value it today.
So not with a sinking fund then. So no need for a sinking fund because you're just looking at as at today.
There is an allowance for repairs and maintenance but it's not appropriate to have a large sinking fund as has been demonstrated in the evidence.
Well I'm not sure about that but I'm interested in what the argument is and what the point is.
So your argument is or your position is it's not necessary or appropriate to have a sinking fund because one's looking at new build.
Exactly.
Okay but if it's a new build like this scheme and you're a metzena or some other operator then you're looking ahead aren't you Mr. Mello -Browning?
You're looking ahead for what may happen to the roof or what may happen to the windows.
Have you ever had a discussion with an operator about sinking funds and how they work?
I don't think it's...
Have you ever had a discussion with them about how they provide for bigger repairs that may
need to be made?
I have had discussions with Cushman and Wakefield who represent many operators who have advised
that a sinking fund is a reserve for future capital expenditure.
It's not a recurring cost of operating a PBSA scheme.
Not what I'm putting to you.
I can see how this has arisen.
I think it's pretty clear, having heard this exchange.
Cushman and Wakefield ask about OPEX.
They don't think that sinking funds are part of OPEX,
and so they don't include them.
I'm putting to you the real world point that Mr Brown,
from his knowledge and experience, has raised,
which is if you're Metzena saying you take over this scheme,
has just been finished, you don't think, oh well, won't provide at all for any bigger
repair that might need to be made in five years or whatever?
My evidence within my rebuttal evidence, my proof of evidence with the letter from Cushman
and Wakefield sets out why I disagree that a sinking fund should be included within a
new build PBSA asset.
My current note is that you don't have anywhere in your assessment a sinking fund type allowance.
Is that accurate?
Yeah, I don't know.
Thank you sir.
You're quite right, so I was exploring why that's the case rather than establishing that.
Thank you very much.
Sir, I am just about to move to a wholly new topic which will definitely take us well beyond
one, so this is probably a suitable convenient place to pause.
Yes, yes, of course.
It feels to me like tomorrow is just going to be yourself and Mr Brown and probably his office.
But most of the comments I've missed is...
No, Mr. Ticliany.
Phil probably won't get onto him?
No, I think it's unlikely. It's a good point. He needn't come, I think, if that's the decision.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think we need to have a bit of a technical finding.
I think so. If we, I'm just looking at Tuesday, I know there's a number of witnesses, but
if the time estimates are adhered to, we should be able to even fit in Cozumel into Tuesday,
although it would be pretty packed, so hopefully we should be able to finish, but we might
end up doing a few late finishes, I can pursue that.